OpenContracts

Temple Quay, Plot 3 Infrastructure Works

Homes & Communities Agency Complete Contract award

Buyer
Homes & Communities Agency
Estimated value
£1,300,000 as published; Contracts Finder does not say whether VAT is included
Awarded value
£1,158,644 as published, VAT not stated
Category
Works
CPV code
45200000 Works for complete or part construction and civil engineering work
First published
15 Jan 2016
Last updated
15 Jan 2016
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

The Plot 3 Infrastructure works around Temple Quay being approximately 3,000m2 of pavement construction, generally comprise of stone capping with tarmac sub-base, sand and block paving, and associated works will include the following components:

• Earthworks
• Extension of Friary to Meads Reach Bridge
o This work would comprise the extension of Friary as a two carriageway road east of Isambard Walk to Meads Reach Bridge.
o As part of this work the footway to the north of Friary (adjacent to the Plot 3 development site) would be extended to 6 metres in width, as will the footway to the south (adjacent to the station) would be made 8.5 metres in width and include the provision of 6 new benches and an avenue of 5 new trees.
o The Friary will terminate with the provision of a new flexible use open space

• Flexible Open Space
o Space for temporary use will also be provided between the extended Friary and the listed retaining wall (outside of development area)
o The area will be finished with seating terraces, and a planted bank to tie into the existing levels forming an earth retaining structure.
o This area will also need to be made capable of accommodating the occasional vehicle turning.

• Opening Isambard Walk as a two-way vehicular street between Friary and Temple Back East
o The existing pedestrianised Isambard Walk will be opened for two-way vehicle access to create a link between Temple Back East and Friary, and to tie in with the existing road of the private estate. As part of this work a new footway will also be provided to the eastern side of the Isambard Walk new carriageway.
o Isambard Walk will act as a shared space, and so will be treated to reduce the potential dominance of vehicles and reduce vehicle speeds
o The footway, trees, cycle parking and street furniture to the west of Isambard Walk and in The Square would remain as existing.

• Temple Back East
o The existing turning head area on Temple Back East would be removed, to allow two way vehicular access to Isambard Walk
o Two way vehicular access will be maintained to Rope Walk, with a left turn out of Rope Walk into Isambard Walk to be provided for
o Existing crossing will be maintained across from The Square to the footway on Temple Back East

Awards

SupplierValueDateStatus
Dyer and Butler £1,158,644 17 Mar 2016 Active

Notices

  1. 15 Jan 2016 Contract award

Contracts Finder holds the official notices, with their documents and contact details.

Data