OpenContracts

Redevelopment of EYFS Outdoor Area

St Gilbert's Church Of England Primary School Active Tender notice

Buyer
St Gilbert's Church Of England Primary School
Estimated value
£30,000 as published; Contracts Finder does not say whether VAT is included
Procedure
Open procedure (below threshold)
Category
Works
CPV code
44100000 Construction materials and associated items
First published
31 Jan 2025
Last updated
31 Jan 2025
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

1 Introduction

1.1 Company Background
St Gilbert's Church of England Primary School (known as 'the School') is a standalone primary academy. Academy status was granted in January 2013.

Located to the West of the historic town centre of Stamford, the school currently has 300 pupils form 4 - 11 years of age.

The current school buildings were established in the early 1970's with a further addition at the beginning of the 2000's.

'The School' is currently rated 'Good' by OFSTED


1.2 Project Background
The existing outdoor play area was installed circa 2008/9 and included:
• Wet pour safe play surface throughout
• Outdoor secure storage for resources
• Activity areas and play equipment

The equipment is now at the end of its economic life and 'the School' are looking to redesign the existing area with a space that is inviting and inspirational for the pupils in the Reception phase of the school

1.3 High Level Overview of Requirements
Bidders are asked to submit a formal tender for the redevelopment of the Early Years outdoor play area

.
1.4 Existing Provision
The existing provision has the following equipment installed:
• Wooden picket boundary fencing
• Wet pour safe play surface throughout
• Central climbing frame and slide
• Sand pit
• Mud pit with activity panels
• Secure storage for outdoor resources
• Raised bed planter
• Covered activity area

See appendix 1 for photographs of the existing provision

To create and inviting and inspirational outdoor play area for use by pupils in the Early Years (Reception) phase.

Key requirements are:

• Removal/recycling of existing facilities including surfacing and timber structures
• Ensuring compliant foundations for any new surfacing or structures
• Design service to be completed in collaboration with 'the School'
• Provision of equipment that will aid the physical development of all pupils
• Provision of equipment that will encourage the joy of learning
• Provision of equipment that enables creativity in play
• Creative design that will enhance the natural world
• A safe play surface and equipment compliant with BSEN1176 and BSEN1177
• Where possible, as much of the materials to be used are from recycled or sustainable sources
• Provision of a full maintenance schedule
• Use of qualified/registered installers
• All contractors to be DBS checked

Notices

  1. 31 Jan 2025 Tender notice

Contracts Finder holds the official notices, with their documents and contact details.