Sudlows Limited
- Awards
- 7
- Value outside frameworks
- £8m
- Framework places
- 0
Values exclude VAT where the notices give it, and only values in pounds are added up. A framework place carries the framework's whole ceiling, shared with the other suppliers on it, so framework places are counted rather than added up.
Awards
| Procurement | Buyer | Value | Date |
|---|---|---|---|
| Substation 3 Pilgrim Hospital Boston | United Lincolnshire Teaching Hospitals NHS Trust | £991,751 | 24 Mar 2026 |
| Substation 3 PHB - Main switchboard & containerisation of the generator | United Lincolnshire Teaching Hospitals NHS Trust | £450,000 | 20 Feb 2026 |
| High Voltage Capital Upgrades 2025-2026 | United Lincolnshire Teaching Hospitals NHS Trust | £1,200,000 | 20 Feb 2026 |
| Stage 2 Principal Contractor - Substation One Works | United Lincolnshire Teaching Hospital NHS Trust | £3,200,000 | 9 Jan 2026 |
| Pilgrim Substation Stage 1 design | United Lincolnshire Teaching Hospitals NHS Trust | £100,000 | 1 Dec 2025 |
| Specialist HV Principal Contractor - Stage 1 | United Lincolnshire Hospitals NHS Trust | £150,000 | 27 Nov 2025 |
| High Voltage Infrastructure | United Lincolnshire Teaching Hospitals NHS Trust | £1,868,005 | 10 Oct 2024 |
Top buyers
| Buyer | Awards | Value |
|---|---|---|
| United Lincolnshire Teaching Hospitals NHS Trust | 5 | £4,609,756 |
| United Lincolnshire Teaching Hospital NHS Trust | 1 | £3,200,000 |
| United Lincolnshire Hospitals NHS Trust | 1 | £150,000 |
By number of awards. Value is the total of awards made to this supplier alone outside frameworks, excluding VAT where the notices give it.