JBA Engineering Limited
- Awards
- 9
- Value outside frameworks
- £429k
- Framework places
- 4
Values exclude VAT where the notices give it, and only values in pounds are added up. A framework place carries the framework's whole ceiling, shared with the other suppliers on it, so framework places are counted rather than added up.
Awards
| Procurement | Buyer | Value | Date |
|---|---|---|---|
| Power Supply Upgrade for Clean Steam Generator for NIBF1 | Centre For Process Innovation Limited | £69,829 | 31 Mar 2026 |
| General Engineering Works Lot 2 framework | Centre For Process Innovation Limited | £500,000 | 10 Dec 2025 |
| General Engineering Works Lot 3 framework | Centre For Process Innovation Limited | £500,000 | 10 Dec 2025 |
| General Engineering Works Lot 4 framework | Centre For Process Innovation Limited | £1,500,000 | 10 Dec 2025 |
| General Engineering Works Lot 5 framework | Centre For Process Innovation Limited | £1,000,000 | 10 Dec 2025 |
| Engineering Services | Centre For Process Innovation Limited | £120,874 | 24 Jan 2024 |
| Award of Contract for Pressure Vessel Manufacture | Offshore Renewable Energy Catapult | £68,500 | 9 Oct 2019 |
| COMAH Report | South Tees Site Company Limited | £20,025 | 29 May 2018 |
| Contract Variation - Duration only - Fault Study | South Tees Site Company Limited | £150,000 | 28 Mar 2018 |
Top buyers
| Buyer | Awards | Value |
|---|---|---|
| Centre For Process Innovation Limited | 6 | £190,703 |
| South Tees Site Company Limited | 2 | £170,025 |
| Offshore Renewable Energy Catapult | 1 | £68,500 |
By number of awards. Value is the total of awards made to this supplier alone outside frameworks, excluding VAT where the notices give it.