Balfour Beatty Utility Solutions Limited
- Awards
- 3
- Value outside frameworks
- £167k
- Framework places
- 2
Values exclude VAT where the notices give it, and only values in pounds are added up. A framework place carries the framework's whole ceiling, shared with the other suppliers on it, so framework places are counted rather than added up.
Awards
| Procurement | Buyer | Value | Date |
|---|---|---|---|
| Major Projects QUDM framework | National Grid UK Limited | - | 26 Oct 2026 |
| 66/132kV Cable Installation Framework framework | National Grid UK Limited | £80,000,000 | 25 Jun 2026 |
| Redcar Power Station 66kV Cable Diversion | South Tees Site Company Limited | £167,158 | 20 Aug 2022 |
Top buyers
| Buyer | Awards | Value |
|---|---|---|
| National Grid UK Limited | 2 | - |
| South Tees Site Company Limited | 1 | £167,158 |
By number of awards. Value is the total of awards made to this supplier alone outside frameworks, excluding VAT where the notices give it.