- Awards
- 19
- Value outside frameworks
- £42.6m
- Framework places
- 7
Values exclude VAT where the notices give it, and only values in pounds are added up. A framework place carries the framework's whole ceiling, shared with the other suppliers on it, so framework places are counted rather than added up.
Awards
| Procurement | Buyer | Value | Date |
| RIP - Design PCF stages 3 and 4 - PACKAGE L - East |
Highways Agency |
£19,920,000 |
27 Feb 2017 |
| RIP - Design PCF stages 3 and 4 - PACKAGE E - Midlands |
Highways Agency |
£11,560,000 |
27 Feb 2017 |
| Smart Motorways Programme Design Package 5 (M62 Junction 10 to 12 and M6 Junction 21a to 26) |
The Department For Transport |
£2,769,375 |
11 Jan 2017 |
| SMP Tranche 3 and 4 Design Package 5- M6 J21a to 26 |
Highways Agency |
£1,646,224 |
10 Jan 2017 |
| AS14 Schemes PCF Stage 2 - A47 /A12 Junctions |
Highways Agency |
£910,000 |
20 Dec 2016 |
| AS14 SAchemes PCF Stage 2 - A47 Thickthorn |
Highways Agency |
£400,000 |
20 Dec 2016 |
| CDF PC1 0073 OD East Capital Delivery |
Highways Agency |
£1,250,000 |
19 Dec 2016 |
| A38 Derby Junctions - Designer appointment |
Highways Agency |
£1,418,837 |
19 Dec 2016 |
| A38 Derby Junctions |
Highways Agency |
£1,418,837 |
18 Dec 2016 |
| PSF PO 1507 Area 12 - M181 Terminal Junction/M181 Motorway De-Trunking Detailed Design |
The Department For Transport |
£536,781 |
4 Apr 2016 |
| AS14 Phase 2- Options Selection- Midlands |
Highways Agency |
- |
16 Mar 2016 |
| Project Support Framework (Consultancy): AS14 Schemes East - A47 Thickthorn Interchange framework |
Highways Agency |
£718,568 |
26 Jan 2016 |
| Project Support Framework (Consultancy): AS14 Schemes East - A47/A12 Junctions framework |
Highways Agency |
£701,737 |
26 Jan 2016 |
| Project Support Framework (Consultancy): AS14 Schemes East - A47 Blofield to North Burlingham upgrade framework |
Highways Agency |
£606,432 |
26 Jan 2016 |
| Project Support Framework (Consultancy): AS14 Schemes East - A47 Guyhirn Junction framework |
Highways Agency |
£581,859 |
25 Jan 2016 |
| Project Support Framework (Consultancy): AS14 Schemes East - A47 North Tuddenham to Easton Dualling framework |
Highways Agency |
£697,977 |
25 Jan 2016 |
| Project Support Framework (Consultancy): AS14 Schemes East - A47 Wansford Junction (A1) to Sutton Dualling framework |
Highways Agency |
£667,741 |
25 Jan 2016 |
| Project Support Framework (Consultancy): AS14 Schemes East Midlands - A52 Nottingham Junctions framework |
Highways Agency |
£1,120,000 |
23 Nov 2015 |
| Regional Investment Programme (Midlands) AS14 Schemes |
Highways Agency |
£751,000 |
27 Oct 2015 |
Top buyers