OpenContracts

WP57 - Anti Graffiti

Skanska Infrastructure (Rail) Complete Contract award

Buyer
Skanska Infrastructure (Rail)
Estimated value
£25,000 as published; Contracts Finder does not say whether VAT is included
Awarded value
£28,000 as published, VAT not stated
Category
Services
CPV code
45221112 Railway bridge construction work
First published
14 Oct 2021
Last updated
22 Apr 2022
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

Apply Anti-Graffiti to below Bridge Structures in Railway environment:
- NE & SE Wingwall (including precast elements)
- East Abutment (including Stage 1, precast, and stage 2 pours)
- West Abutment Caisson Cap
- West Abutment Stem (including bearing plinths)
- Ballast Wall (front face only. 2no.)
- Bearing Plinths
- Diaphragm Wall
- Robust Kerb

- All coatings to be applied in accordance with 146588-SKA-SPE-ECV-000012
- Treatment is to be either Epicuro Hydrophobic Bridgeguard or Parex Paraguard

Tenderers will be issued a formal invitation to tender (ITT) with a pricing and submission document to complete.

The submission will included a balanced scorecard requesting answers to questions (along with evidence) to be submitted for review and scoring. The highest scoring tenderers will be considered preferred tenderer for the works. High level criterial of the balanced scorecard questions will include:
- Quality
- Sustainability
- Competence
- Commercial Price
- Etc

Mid tender reviews will be held prior to the submission deadline to review the scope of works with the SAS13 project team. Following the submission deadline, there will be post tender reviews to review your submissions with the SAS13 project team.

Best and final offers may be requested from tenderers.
Skanska have been employed by Network Rail (NR) to replace the existing SAS 13 bridge to increase lateral clearance below the structure to enable the construction of HS2's new depot access lines and access to the new HS2 depot via road. The existing bridge forms the rail intersection between the Stechford to Aston (SAS) line and the Birmingham to Derby Line (DBP3).

The new bridge will be a 92m single spanning structure. Skanska's appointment by Network Rail includes the design and demolition of the existing bridge and installation of the new structure.

Awards

SupplierValueDateStatus
Not named £28,000 1 Jan 2022 Active

Notices

  1. 14 Oct 2021 Tender notice
  2. 22 Apr 2022 Contract award

Contracts Finder holds the official notices, with their documents and contact details.

Data