Wansford - Earthworks ECI
galliford try Planning Planned procurement
- Buyer
- galliford try
- CPV code
44000000Construction structures and materials; auxiliary products to construction (except electric apparatus)- First published
- 13 Dec 2021
- Last updated
- 13 Dec 2021
- Rules
- Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds
Description
NOTIFICATION OF SUBCONTRACT PACKAGE
A47 Wansford to Sutton
Galliford Try, as one of the East Region Delivery Integration Partners, are delivering the A47 Wansford project in the county of Cambridgeshire on behalf of National Highways. This project involves the dualling of the existing A47 between the A1/A47 junction Wansford to the Nene Way Roundabout at Sutton, which is part of major improvements to the existing A47.
The project has recently submitted a Development Consent Order to the Planning Inspectorate and the project is forecast to commence on site in March 2023 and will take around 1-2 years to complete.
Package: Earthworks
Outline Scope of Works
The Earthworks Package consists of two parts:
Stage 1: Early Contractor Involvement. To provide technical and commercial input into the detailed design phase and to formulate the budget and programme for the works.
Stage 2: Construction. To provide all necessary supervision, labour, plant and materials required to undertake the earthworks comprising the excavation, processing, placement and compaction of site won soils and the Import of suitable fill material to form the development platform to support the new road, structures and landscaping. The contractor will also be responsible for the disposal to stockpile or off site of any unacceptable or surplus soils and other materials generated during the bulk earthworks.
Principal Activities Approximate Quantities
Excavation of Class 5A 70,000m3
Excavation Excl Class 5A 130,000m3
Deposition of Fill 103,000m3
Imported Class 6F5 Capping 44,000m3
Disposal of material excl Class 5A 27,000m3
Disposal of Class 5A Material 40,000m3
Topsoiling 30,000m3
Programme
It is currently anticipated that the Stage 1 ECI works will commence in February 2022.
Timings
Deadline for Notifications of Interest 16:00 hrs on Wednesday 22nd December 2021
Galliford Try procurement process
To secure work with Galliford Try, a supplier will need to pass the PAS91 onboarding process administered through Builders Profile. Details will be shared with shortlisted suppliers.
If this package is of interest to your company please contact our procurement team by e-mail via the following email address: [email removed], by the above deadline with your notification of interest and details of your capabilities.
Any notifications of interest after the above deadline will not be responded to.