Under Track Crossing of Utilities - Old Oak Common (S4) Station - HS2
Balfour Beatty VINCI Systra JV Complete Contract award
- Buyer
- Balfour Beatty VINCI Systra JV
- Estimated value
- £10,000,000 as published; Contracts Finder does not say whether VAT is included
- Category
- Works
- CPV code
45221200Construction work for tunnels, shafts and subways- First published
- 19 Dec 2019
- Last updated
- 2 Nov 2020
- Rules
- Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds
Description
Under Track Crossing of Utilities
8 Nr pipejacks under the GWML and North Depot railway to carry diverted utilities
The UTX will be formed of 8 No. 1.2m internal diameter precast concrete pipes jacked through the ground below the GWML and North Pole (IEP) railway lines. Seven of the bores are to be constructed from a temporary steel sheet piled launch pit located adjacent to OOCL within the decommissioned Hex depot. They will be jacked approximately 175m to a reception pit located within the Wormwood Scrubs common land just south of the boundary to the IEP depot.
The eighth bore, which is nearest to Old Oak Common Lane, is to be driven from reception pit located within Wormwood Scrubs land. This 160m long bore will terminate in a reception pit constructed just north of the out of use Down/Up Wycombe Line, railway embankment and adjacent to Old Oak Common Lane
Commence works on site July 2020 with the construction of launch and reception pits, including site establishment by the sub-contractor. Commence pipe jacking October 2020, complete December 2020. Prior to this works the sub- contractor shall complete detailed planning, SHEQ documentation approval with all parties, temporary works design and approvals, fabrication design and approvals.
The selected Supply Chain Partner must be able to demonstrate:
Thames Water approved contractor
Micro boring Specialist
Deep Drainage
Temporary Works
Working in railway environment
Dimensional Control
About the buyer's selection process:
Respondents to this opportunity should be advised that shortlisted applicants will be invited to tender through an external ERP system.
The exact scoring criteria are currently being developed by BBVS, and shortlisted suppliers will be invited to register for the ERP system in due course.
What is clear at this stage is that tenders will be scored competitively across a range of criteria, such as, but not limited to: HSEQ, Commercial, Programme, Methodology (particularly with working in a track environment).
About the buyer:
In 2018, Balfour Beatty, VINCI and Systra (BBVS) created a strategic alliance to deliver major infrastructure projects for HS2, in particular the Terminus at Old Oak Common.
BBVS are committed to delivering this project to align with the key principles of Integrity, Leadership, Respect & Safety.
Respondents to this opportunity should be advised that shortlisted applicants will be invited to tender through an external ERP system.
The exact scoring criteria are currently being developed by BBVS, and shortlisted suppliers will be invited to register for the ERP system in due course.
What is clear at this stage is that tenders will be scored competitively across a range of criteria, such as, but not limited to: Commercial, Programme, Methodology, HSEQ, Capability and Capacity.
In 2018, Balfour Beatty, VINCI and Systra (BBVS) created a strategic alliance to deliver major infrastructure projects for HS2, in particular the Terminus at Old Oak Common.
Awards
| Supplier | Value | Date | Status |
|---|---|---|---|
| Joseph Gallagher Ltd | - | 21 Oct 2020 | Active |
Notices
- 19 Dec 2019 Tender notice
- 2 Nov 2020 Contract award
Contracts Finder holds the official notices, with their documents and contact details.