The Mayor and Commonalty and Citizens of the City of London Active Tender notice

Buyer
The Mayor and Commonalty and Citizens of the City of London
Estimated value
£1,400,000 excluding VAT; £1,680,000 including VAT
Procedure
Below threshold - open competition
Category
Works
CPV code
45221100 Construction work for bridges
First published
15 Apr 2025
Last updated
22 Apr 2025
Legal basis
Procurement Act 2023

Description

Tower Bridge Mud Tanks – this project will deliver repairs and enhancement works to 6no. mud tanks that form part of the rainwater/surface drainage infrastructure at Tower Bridge, as well as associated repair/enhancement works to improve safety, access, lighting, etc. in the 6no. mud tanks bays, which are situated on the lower levels of the bridge.
Tower Bridge is a bascule bridge and beneath the two towers are the pivot and drive shafts and hydraulic operating machinery. Beneath the main pivot shafts are 6no. mud tanks; 3no. on the north side and 3no. on the south. The tanks serve to collect rainwater, surface run-off, and debris from the bascule arms when raised, to prevent them entering the chambers below. Currently, they regularly block up and overflow, and must be manually monitored and emptied. A condition survey was undertaken in 2017 which identified that all the mud tanks are in poor condition with significant
corrosion identified, and without exception all require repair to some extent.
Each mud tank consists of a front and rear chamber. The rear chambers will be assessed and repaired in situ. The front chambers will be cut out and replaced with a new mild steel chamber with deeper profile, improving the water storing capacity and providing adequate spatial clearanceto moving parts of the bridge. Both chambers will be protected with new GRP lining. Discharge pipework will need alteration and reconnection to the revised tank chambers. Each mud tank will receive new GRP mesh deck hinged covers, to prevent larger debris/detritus entering the tanks/chambers and causing blockages, while still permitting water/runoff to reach the tanks.
Beneath each mud tank lies a platform of original timber planks spanning the bascule chamber. This platform is currently inaccessible due to structural degradation (rot) caused by water overflow from the tanks above. A specialist contractor will assess the strength and condition of the timber planks. If they are deemed sufficient for maintenance loads, the planks will be restored and reused,
while damaged/rotten planks and the timber kerb will be replaced.
Each mud tank bay will also receive new handrails/guardrails to promote safer access, improved LED lighting (mixture of replacement and new/additional), new small power provision, and corrosion treatment/repainting.

Notices

  1. 15 Apr 2025 Preliminary market engagement notice 015272-2025
  2. 22 Apr 2025 Tender notice 016199-2025

Find a Tender holds the official notices, with their documents and contact details.

Data