Thames Tideway Tunnel - C405 Main Works West - Bulkheads (Acton)

BMB Joint Venture (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty) Complete Contract award

Buyer
BMB Joint Venture (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty)
Awarded value
£3,880 as published, VAT not stated
Procedure
Open procedure (below threshold)
Category
Works
CPV code
45262670 Metalworking
First published
8 Jan 2021
Last updated
8 Jan 2021
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

The Thames Tideway Tunnel project (the Project) will control CSO discharges by intercepting and diverting combined sewage flows into a new storage and transfer tunnel. The main tunnel will run from Acton Storm Tanks in west London to Abbey Mills Pumping Station in the east, where it will connect to the Lee Tunnel, which will transfer the combined sewage to Beckton Sewage Treatment Works for treatment. The Project extends from Acton Storm Tanks in west London, to Abbey Mills Pumping Station in east London. The Project includes associated works at Beckton STW, Shad Thames Pumping Station and Bekesbourne Street.

The geographic layout of the Project and local authorities through which it passes is shown in Figure 1.
The Project comprises:
a. tunnels:
i. a main tunnel which will capture and store combined sewage from CSOs along its route and transfer it to Abbey Mills Pumping Station, from where the Lee Tunnel will transfer it for treatment at Beckton Sewage Treatment Works
ii. 11 connection tunnels, which will link flows from CSOs to the main tunnel.
b. Worksites:
i. five main tunnel Worksites (drive and/or reception sites)
ii. 16 CSO Worksites
iii. two System modification Worksites Thames Tideway Tunnel
iv. works at Beckton Sewage Treatment works.

Section 4: Scope of Works

Supply a price for manufacture and deliver 4no. Bulkheads 3 design (i.e. 8 x Panel 3a, 4 x Panel 3b). Weld detail is included in the latest drawing file (Acton Bulkhead Drawing BH3-6 P02 (Latest)).

No construction or manufacture should commence until BMB have confirmed approval of drawings. Approved for construction drawings will be issued as soon as they become available.

All deliveries are to be in accordance with the delivery requirements (FORS).

Returned quotations will be evaluated by BMB JV's (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty) Procurement team in conjunction with our design and engineering teams.
Quotations will be evaluated based on;
Cost
Timeliness of return
Adherence to and demonstration of understanding of the drawings and specifications provided at this point.
Provision of accurate product specifications to accompany the quotation.
Supplier experience of similar projects,evidence of this will be requested should the initial quotation be of interest.
Should the candidate supplier be shortlisted they will then be contacted directly by a member of the BMB Procurement Team within two weeks of shortlisting to discuss the requirement in detail.
BMB Joint Venture (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty)
BMB-JV Tideway West, Acton Storm Tanks, Canham Road, W3 7SR

Additional information: BMB-JV Tideway West, Acton Storm Tanks, Canham Road, W3 7SR

Awards

SupplierValueDateStatus
Not named £3,880 19 Jun 2020 Active

Notices

  1. 8 Jan 2021 Contract award