# Thames Tideway Tunnel - C405 Main Works West - Acton Storm Tanks, Ducting Works

BIP Solutions Limited · Complete · Contract award

- Buyer: BIP Solutions Limited
- Awarded value: £419,198 (VAT not stated)
- Procedure: Open procedure (below threshold)
- Category: Goods
- CPV code: 44163110 Drainage pipes
- First published: 15 August 2019
- Last updated: 15 February 2022
- Rules: before the Procurement Act 2023 (published on Contracts Finder)

## Description

The Thames Tideway Tunnel project (the Project) will control CSO discharges by intercepting and diverting combined sewage flows into a new storage and transfer tunnel. The main tunnel will run from Acton Storm Tanks in west London to Abbey Mills Pumping Station in the east, where it will connect to the Lee Tunnel, which will transfer the combined sewage to Beckton Sewage Treatment Works for treatment. The Project extends from Acton Storm Tanks in west London, to Abbey Mills Pumping Station in east London. The Project includes associated works at Beckton STW, Shad Thames Pumping Station and Bekesbourne Street. 
      
      The geographic layout of the Project and local authorities through which it passes is shown in Figure 1.
      The Project comprises:
      a. tunnels:
      i. a main tunnel which will capture and store combined sewage from CSOs along its route and transfer it to Abbey Mills Pumping Station, from where the Lee Tunnel will transfer it for treatment at Beckton Sewage Treatment Works
      ii. 11 connection tunnels, which will link flows from CSOs to the main tunnel.
      b. Worksites:
      i. five main tunnel Worksites (drive and/or reception sites)
      ii. 16 CSO Worksites
      iii. two System modification Worksites Thames Tideway Tunnel
      iv. works at Beckton Sewage Treatment works.
      
      The Main Works West - Contract 405: all works from and including
      the Acton Storm Tanks shaft to and including the Carnwath Road
      Riverside shaft, as well as the Frogmore connection tunnel from
      Carnwath Road Riverside shaft to King George's Park shaft.
      
      This works package is for the supply and installation of Condensate drains, Air Ventilation ducts and MEICA ducts, throughout the Acton Storm Tanks TTT West site.
      
      Supply and installation of the following:-
      
      Acton Storm Tanks, Ducting Works as shown on the attached drawings.
      
       
       Returned quotations will be evaluated by BMB JV's (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty) Procurement team in conjunction with our design and engineering teams.
      Quotations will be evaluated based on;
      Cost
      Timeliness of return
      Adherence to and demonstration of understanding of the drawings and specifications provided at this point.
      Provision of accurate product specifications to accompany the quotation.
      Supplier experience of similar projects,evidence of this will be requested should the initial quotation be of interest.
      Should the candidate supplier be shortlisted they will then be contacted directly by a member of the BMB Procurement Team within two weeks of shortlisting to discuss the requirement in detail. 
       BMB Joint Venture (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty)

## Awards

| Supplier | Value | Date | Status |
|---|---:|---|---|
| Not named | £419,198 | 21 Jan 2020 | Active |

## Notices

- 15 Aug 2019: Tender notice https://www.contractsfinder.service.gov.uk/Notice/1cb56eae-5946-4710-841f-d6720cd8a8ca
- 15 Feb 2022: Contract award https://www.contractsfinder.service.gov.uk/Notice/2ee26bcf-18e1-49b5-b755-af06a894a3d2

---