Tender Round 6 (TR6) for the grant of three offshore transmission licences
Office of Gas and Electricity Markets Active Tender notice
- Buyer
- Office of Gas and Electricity Markets
- Estimated value
- £2,708,054,532 as published; Contracts Finder does not say whether VAT is included
- Procedure
- Competitive procedure with negotiation (above threshold)
- Category
- Services
- CPV code
65300000Electricity distribution and related services- First published
- 30 Nov 2018
- Last updated
- 30 Nov 2018
- Rules
- Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds
Description
This concerns the proposed grant of three offshore transmission licences to successful bidders to connect three offshore wind farms to the GB onshore grid.
TR6 consists of Beatrice Offshore Wind Farm, Hornsea Project One Offshore Windfarm and East Anglia ONE (the Projects).
The tender process will consist of two stages for each Project: an Enhanced Pre-Qualification (EPQ) stage and an Invitation to Tender (ITT) stage, resulting in selection of preferred bidders. Bidders who qualify at the EPQ stage will 'passport' into the ITT stage for all Projects which it has indicated it will participate. Where the maximum number of qualified bidders has not been reached for a Project, an additional EPQ stage may be run.
Any bidder wishing to participate in the EPQ stage for any Project or in an additional EPQ stage, if held, must express their interest as per the requirements in the EPQ documentation.
Additional information:
TR6 consists of 3 projects, Beatrice Offshore Wind Farm, Hornsea Project One Offshore Wind Farm and East Anglia ONE (the Projects).
The tender process will consist of two stages for each of the Projects: an Enhanced Pre-Qualification (EPQ) stage followed by an Invitation to Tender (ITT) stage which will result in the selection of a preferred bidder. Any bidder that qualifies at the EPQ stage will "passport" into the ITT stage for all of the Projects for which it has indicated it will participate. Where the maximum number of qualified bidders has not been reached for a Project, Ofgem may run an additional EPQ stage.
Any bidder wishing to participate in the EPQ stage for any or all of the Projects or in an additional EPQ stage, if held, must express interest in doing so in accordance with the requirements in the EPQ documentation.
Ofgem intends to stagger the ITT stages based on each Project's date of first power and as a result of the staggering of ITT stages, if an additional EPQ stage is held, any bidders qualifying as a result of that additional EPQ will only be eligible to submit an ITT submission for Projects yet to commence the ITT stage at the time of qualification.
The type of procedure to be adopted is a competitive procedure with negotiation. The subject matter of this notice is the proposed grant of three offshore transmission licences to successful bidders for the purpose of connecting three wind farms to the GB onshore grid.
TR6 consists of three projects. A transmission licence is expected to be granted for each project. High level details about the projects are as follows: Project: Beatrice; Developer: SSE Renewables, Copenhagen Infrastructure Partners, SDIC Power; Limited Capacity(MW): 588. Project: Hornsea Project One Offshore Wind farm; Developer: Ørsted; Limited Capacity (MW): 1,200.Project: East Anglia ONE; Developer: ScottishPower Renewables; Limited Capacity (MW): 714
Requests to participate/EPQ submissions must be made electronically by 12:00 (local time), 07/02/2019 See the above links for how to do this.
Please note that the information contained in the fields 'contract start date', 'Contract end date' and 'Lowest/actual value (£)' in section 1 of this notice are indicative only. Please consult the tender documentation for further details.
Notices
- 30 Nov 2018 Tender notice