OpenContracts

Tender for Southend-on-Sea Town Centre Strategy & Investment Plan

Southend-on-sea Borough Council Complete Contract award

Buyer
Southend-on-sea Borough Council
Awarded value
£115,378 as published, VAT not stated
Procedure
Open procedure (below threshold)
Category
Services
CPV code
70332200 Commercial property management services
First published
15 Oct 2021
Last updated
21 Jan 2022
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

To produce the Southend Town Centre Strategy & Investment plan.

This will include a clear articulation and ambitious proposition for the town centre and will take an innovative culture led regeneration approach. There will be a clear pitch to investors and the work will directly contribute to the preparation of public and private sector bids including submission by the Council to Levelling Up Funding (LUF) round 2.

To produce the Southend Town Centre Strategy & Investment plan.

This will include a clear articulation and ambitious proposition for the town centre and will take an innovative culture led regeneration approach. There will be a clear pitch to investors and the work will directly contribute to the preparation of public and private sector bids including submission by the Council to Levelling Up Funding (LUF) round 2.

The successful bidder will liaise with the LUF round 2 bid writers. LUF bid writing will be procured separately.

Engagement with residents and other key stakeholders will be key to successful delivery of this work, we want to see strong community input and participation.

The work will also provide a programme of actions for delivery.

This work must draw on a review of previous work by the Council and partners: public consultations; collaborative discussions with key stakeholders; town wide analysis and planning; Local Plan review; Culture-led regeneration initiatives; public realm improvements; and current thinking on a proposition for investment in the town. A list of core documents and sources of previous work will be supplied.

We are looking for a short, sharp intervention to build on previous work.

The Southend Town Centre Strategy & Investment Plan - once completed will be launched quickly in spring 2022 to maintain momentum and focus on the town centre.

Deadline for the draft report interim completion work will be Friday 18th March 2022 and full completion of the work will be Friday 27th May 2022.

The opportunity is available via registration at https://procontract.due-north.com

Additional information: Please note this is an electronic tender and messages will be dealt with via the portal's messaging system.

To formally register and bid for this opportunity please go to
https://procontract.due-north.com

Awards

SupplierValueDateStatus
We Made That LLP £115,378 20 Dec 2021 Active

Notices

  1. 15 Oct 2021 Tender notice
  2. 21 Jan 2022 Contract award

Contracts Finder holds the official notices, with their documents and contact details.

Data