OpenContracts

TABS Software licencing + support & maintenance

Network Rail Infrastructure Limited Complete Transparency notice (update)

Buyer
Network Rail Infrastructure Limited
Procedure
Direct award
Category
Services
CPV code
72000000 IT services: consulting, software development, Internet and support
First published
17 Jun 2025
Last updated
17 Jun 2025
Legal basis
Procurement Act 2023

Description

This requirement is for a three year renewal for the Microgen Aptitude Software Licence, Maintenance and Support Agreement with Aptitude Software Limited via a Single Tender Action (STA) commencing on 23/06/2025.
The “Track access billing programme” has been established within Route Services IT to deliver a consolidated software application, database and infrastructure for the recording of Track Access, Compensation Payments (Planned and Unplanned) and the maintenance of reference data. The Billing programme is a strategic programme to improve the way in which the billing function for Network Rail (NR) is carried out and managed by the organisation.
As a longstanding client of Aptitude since 2008, Network Rail has leveraged Aptitude
Software Limited platform to support critical internal operations through a customised application built and maintained using the Aptitude Platform.
Key Areas of Support:
• Web Application Development
Network Rail uses the Aptitude Platform’s web application generator to develop and operate an internal application. Uniquely, they run their environment on Microsoft Windows, utilising IIS (Internet Information Services) and .NET technologies, rather than the more common Linux-based setup.
• Calculation Capability
The platform supports core business calculations - specifically, those used to model and determine the fees other companies must pay to access and use railway infrastructure. These financial models are essential to Network Rail’s operations.
• Ongoing Upgrades and Technical Support
Aptitude has supported several platform upgrades over the years, with the most recent migration to version 24.4.1. We assisted in resolving issues during this process, particularly compatibility concerns with Windows Server 2022.
• Testing and Migration Status
Network Rail is in the final phase of testing their newly upgraded application. Most system tests have been completed successfully, with a few final validations currently underway.
• Continued Engagement
While direct development work has been minimal since 2019, Aptitude
continues to provide proactive technical support, version upgrades, and assistance with troubleshooting to ensure continued platform stability.

Awards

SupplierValueDateStatus
Not named £827,198 17 Jun 2025 Pending

Notices

  1. 17 Jun 2025 Transparency notice 032921-2025
  2. 17 Jun 2025 Transparency notice (update) 032937-2025

Find a Tender holds the official notices, with their documents and contact details.

Data