SZC CWA - Pool Bunker Construction

Sizewell C Limited Open for tenders Tender notice

Buyer
Sizewell C Limited
Tender deadline
25 Nov 2026, 14:30
Estimated value
£20,000,000 as published; Contracts Finder does not say whether VAT is included
Category
Goods
CPV code
45210000 Building construction work
First published
19 Nov 2026
Last updated
19 Nov 2026
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

The contract will deliver a commissioned, weathertight and operational Pool Bunker above the base slab. The facility will support assembly, welding and inspection activities before modules are transferred to the Nuclear Island.

The scope of works includes:
• Primary steel frame and crane runway beams.
• Rainscreen cladding and industrial doors, with precast cladding retained as the alternative envelope.
• Five-section retractable roof.
• Secondary steelwork platforms, working levels and access arrangements.
• Mechanical, electrical and public health services, including local exhaust ventilation, power, lighting and controls.
• Passenger and goods hoists, stair cores and roof access.
• Installation and commissioning of three free-issued gantry cranes.
• Tented workshop, lightning protection and earthing.
• Testing, commissioning, quality records and formal handover.

The base slab and the separate site non-destructive testing contract are outside this sourcing strategy. Their interfaces will be defined in the tender documents and managed through the contract programme.

The key scope deliverables are:
• Completed design to RIBA stage 4 and coordinated construction information.
• Approved contractor programme aligned to project milestones.
• Constructed and commissioned Pool Bunker, including roof, cranes, platforms, access and building services.
• Completed health, safety, quality and assurance records.
• Demonstrated interfaces with the base slab, utilities and non-destructive testing arrangements.
• Formal handover following operational readiness review.

The timescales are as follows:

The Pool Bunker is required to support the planned assembly, welding and inspection of pool and tank liner modules before transfer to the Nuclear Island. The current estimated site construction period is:
• 40 weeks for the preferred rainscreen and Safe RAD solution.
• 46 weeks for the 275 mm precast fallback solution.

The current target is for the Pool Bunker to be completed and handed over by 28 February 2028, ready to support the planned assembly, welding and inspection of pool and tank liner modules. The programme is dependent on completion of the base slab and availability of the K10 area and will be revalidated once the K10 release date is confirmed.

Notices

  1. 19 Nov 2026 Tender notice

Contracts Finder holds the official notices, with their documents and contact details.