# Supply Chain Notice: WAT-0044-02- Design and Install a Tug Berth Pontoon Replacement

Ministry of Defence · Planning · Planned procurement

- Buyer: Ministry of Defence
- CPV code: 45241300 Pier construction work
- First published: 24 July 2023
- Last updated: 24 July 2023
- Rules: before the Procurement Act 2023 (published on Contracts Finder)

## Description

The Tenderer should be aware that the works detailed in this package are constrained due to the nature of the location they are to be conducted in. 

Project location

HM Naval Base Portsmouth
The Contractor shall be expected to adhere by the HMNB site security requirements, all Contractors and Sub-Contractors shall be BPSS security vetted and will be required to hold the relevant site security passes.
The Contractor shall be expected to hold the following levels of insurance £10m Public Liability, £10m Product Liability, £5m Professional Indemnity

KBS Maritime - Introduction
KBS Maritime is a joint venture between KBR and BAE Systems, bringing together two global players with a rich heritage of delivering excellence, innovation and reliability. The joint venture will combine the expertise of KBR as a global leader in infrastructure asset management and services with BAE Systems&apos; experience and capability within Portsmouth Naval Base. KBS Maritime are delivering an ambitious, modern and enduring change to the Portsmouth Naval base infrastructure, securing investment in the local community and ensuring fit-for-purpose, world-leading fleet support for the Royal Navy and the UK in the decades ahead.

Project Background
KBS Maritime have a requirement to design and install a berthing pontoon and structure to support the tug operations relating to Portsmouth Naval Base. The pontoons shall have the compatibility to interchange between the existing structure and the newly designed installation. For the newly designed structure, the Contractor shall assume a piled retention system with a max berthing force requirement of 800T. The design and subsequent works will require an investigation/survey of the seabed; construction of the civil engineering enabling works; installation (including mechanical and electrical services). Additionally, the removal and disposal of the existing pontoon and piles shall be considered.

Key Dates (approximate)
Expressions of Interest: 08 August 2023
ITT Published: 14 August 2023
ITT Close: 28 September 2023
Bidders Selected: 31 October 2023
Construction commencement: Nov 2023
Construction Completion: TBC
 

Additional information: 
If you are interested in this opportunity, please contact Paul Homshaw - at [email removed] to express interest, quoting ref WAT-0044-02 Design and Install a Tug Berth Pontoon Replacement. 

Please also visit Asite Marketplace to register as a supplier. Once registered / if you are already a registered user, please email [email removed] to be added to our connected supply list, quoting full Company Name.

Once the notice has closed, suppliers will be invited to Pre-Qualify and/or Invited to Tender. Open or restricted tender procedure will be dependent on the number of expressions of interest received. A Non-Disclosure Agreement will also be required, prior to participating in a Pre Qualification and/or Invitation to Tender

## Notices

- 24 Jul 2023: Planned procurement https://www.contractsfinder.service.gov.uk/Notice/768be75b-9f6e-4a47-b2ab-a214f249c498

---
Page: https://opencontracts.uk/contract/supply-chain-notice-wat-0044-02-design-and-install-a-tug-berth-af2329c4-fa17-42f6-9acd-89f0ca185036
Contains public sector information licensed under the Open Government Licence v3.0. Source: Find a Tender and Contracts Finder, Cabinet Office.