OpenContracts

Supply Chain Notice: EOI - BLD-0109-01 Workshop relocation

Ministry of Defence Planning Planned procurement

Buyer
Ministry of Defence
CPV code
45213252 Workshops construction work
First published
4 May 2023
Last updated
4 May 2023
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

HM Naval Base Portsmouth

The Supplier shall be expected to adhere by the HMNB site security requirements, all suppliers and Sub-Contractors visiting site shall be BPSS security vetted and will be required to hold the relevant site security passes.

KBS Maritime EOI - BLD-0109-01 Workshop relocation

KBS Maritime is a joint venture between KBR and BAE Systems, bringing together two global players with a rich heritage of delivering excellence, innovation and reliability. Part of the UK Ministry of Defence's (MOD) Future Maritime Support Programme (FMSP), KBS Maritime will provide technology-led and data-driven facilities management and dockside services at the base.

Undertake a planning exercise (with the detailed input of building users) to determine the exact quantities of the significant stock that are to be moved into each new location. This is to include requirements for moving existing racking and any new storage racking if required. Area circa £1000m2.
Undertake a planning exercise with the building users to determine how ownership of stock shall be passed between building owner and contractor during the works, and the process for continuous ('live') documentation, stock taking, and active stock location.
Undertake a review of space requirement for items of equipment (band saw, guillotine, etc.) being moved including MHE track-runs, and parking space requirements.
Undertake a review of the electrical and structural requirements for items of equipment being moved from and adequacy of the existing electrical infrastructure in the new locations.
Undertake a review of the proposed gas bottle storage area, ensuring compliance with the relevant gas storage standards. (250 gas bottles)
Detailed plan showing exactly where the stock, racking, and equipment is to be relocated within the new locations. This shall include a proposed sequence of relocation works.
The Contractor is responsible for design, installation, and inspections, of all temporary works required to safely undertake works.
The contractor is to undertake the duties of Temporary Works coordinator on behalf of KBS Maritime.
The Contractor is responsible for design, installation, and inspections, of all temporary works required to safely undertake works. The contractor is to undertake the duties of Temporary Works coordinator on behalf of KBS Maritime. All temporary works design is to be issued to KBS Maritime for comment prior to erection/installation.

Additional information:
If you are interested in this opportunity, please contact

Norma Shepherd at [email removed]
quoting ref EOI BLD-0109-01 Workshop Relocation HMNB in subject line.

to request a Pre-Qualification Questionnaire

Notices

  1. 4 May 2023 Planned procurement

Contracts Finder holds the official notices, with their documents and contact details.

Data