SUPPLY CHAIN NOTICE - Central Substation RIBA4 & Build

Ministry of Defence Planned Planned procurement

Buyer
Ministry of Defence
Estimated value
£1,300,000 as published; Contracts Finder does not say whether VAT is included
CPV code
45232220 Substation construction work
First published
19 Mar 2026
Last updated
19 Mar 2026
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

The overarching requirement of the project is to develop the RIBA Stage 3 Design into a complete RIBA Stage 4 Technical Design and subsequently build and commission the new Central Substation building (through RIBA Stage 5 and 6).
This project is split into two principal Phases as outlined below - a Design Phase (1) and a Build Phase (2), each with their own corresponding Work Packages.

In summary, this Project includes the following work packages:

Project Phase 1 (Design) includes the following work packages:
- WP 1: Survey and assessment work to facilitate the RIBA 4 design.
- WP 2: RIBA 4 Technical Design incl. all temporary works designs.
- WP 3: Undertake earthing design for Central Substation.
Project Phase 2 (Build) includes the following work package:
- WP 4: RIBA 5 and 6: Construct, Commission and Handover the works as designed in Phase 1.

Installation of HV/LV Electrical switch panels and associated cabling shall not form part of this work, and will follow as a separate project once WP 4 is complete.

Those that meet the criteria of this initial phase will be invited to participate in a final competition. Deadlines for expressions of interest are the 27th March. Any expressions received after this date will not be accepted.