South MRT Phase 1b and 2 - AWARD

Reading Borough Council Complete Contract award update

Buyer
Reading Borough Council
Estimated value
£5,000,000 as published; Contracts Finder does not say whether VAT is included
Awarded value
£2,747,821 as published, VAT not stated
Procedure
Open procedure
Category
Works
CPV code
45233100 Construction work for highways, roads
First published
11 May 2017
Last updated
11 May 2017
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

Reading Borough Council is seeking an experienced highways contractor to undertake the next phase of works as part of the Councils 'Mass Rapid Transit (MRT) South Scheme'.

The scheme consists of a series of highway improvements along the A33 corridor, focussed on improving public transport journey times. The 'MRT South' will link central Reading town centre to existing / proposed residential and employment areas to the south of Reading including Green Park and the new Mereoak Park and Ride facility.

The phase being advertised as part of this procurement exercise is 'Phase 1b and 2'

The tender documents contain proposals for a \"core scheme\" as well as the possible \"additional works\". These additional works may be instructed at the commencement of the Contract, or by way of variation to the Contract during the construction period. For the avoidance of doubt the Council intends to initially award a contract for the \"core scheme\" only and as such will conduct this tender assessment considering the \"core scheme\" only.

The \"core scheme\" works in Phase 1B comprise the following elements:

• Widening of the A33 to create a new bus lane in the south bound direction from Bennet Road Gyratory junction to Imperial Way junction. The road widening occurs largely adjacent to the existing carriageway in verges owned by the highway authority.

• Amendments to the traffic signal pedestrian crossings within the works and incorporation of a new traffic signal controlled bus priority junction in the southbound lane immediately prior to the Imperial Way Roundabout.

• Associated with the above are site clearance (including taking down of kerbs, traffic signs, lighting and street furniture etc), vehicle restraint systems, surface water drainage, earthworks, kerbing, paving and road surfacing, traffic signals and street lighting.

• Adjustments to Statutory utility equipment.


The \"core scheme\" works in Phase 2 comprise the following elements:

• Widening of the A33 to create a new bus lane in the south bound direction from Kennet Island junction to Bennet Road Gyratory junction. The road widening occurs largely adjacent to the existing carriageway in verges owned by the highway authority.

• Associated with the above are site clearance (including taking down of kerbs, traffic signs, lighting and street furniture etc), vehicle restraint systems, surface water drainage, earthworks, kerbing, paving and road surfacing, traffic signals and street lighting.

• Adjustments to Statutory utility equipment.

Awards

SupplierValueDateStatus
Wills Bros Civil Engineering Ltd £2,747,821 20 Mar 2017 Active

Notices

  1. 11 May 2017 Contract award
  2. 11 May 2017 Contract award update