Skerryvore Lighthouse Major Refurbishment

Northern Lighthouse Board Planned Pipeline notice

Buyer
Northern Lighthouse Board
Estimated value
£1,800,000 excluding VAT; £2,160,000 including VAT
Procedure
Below threshold - open competition
Category
Works
CPV code
45453100 Refurbishment work
First published
23 Nov 2026
Last updated
23 Nov 2026
Legal basis
Procurement Act 2023

Description

The NLB are seeking to appoint a Principal Contactor to plan and manage the full refurbishment of Skerryvore Lighthouse, the works are expected to take around 4 years working in the summer months only, with the contractors living in a camp based on Hynish, Tiree. The works will be in 5 distinct phases.
Camp Set Up
The Principal Contractor will be required to set up a semi-permanent site camp, with designated site office, welfare facilities and lie in accommodation for the duration of the project.
Strip-Out.
The eleven-storey granite tower is to be completely stripped out back to bare stone. This will include the removal of existing steel fuel tanks, water tanks, all partitions, diesel generators and all fixtures and fittings. The internal walls of the tower have previously been sprayed with Gunite, and asbestos containing material, as part of the initial strip out a registered asbestos removal company will require to be sub-contracted to removal all remaining traces of the Gunite on each floor.
Solar Installation.
The new Optic for Skerryvore it to be solar powered. To do this a cantilevered aluminium platform will be erected from the lighthouse balcony, this will support at 24 panel solar array, also constructed from aluminium. The solar gain will charge a battery bank housed in one of the 11 levels which will in turn run the optic. At this stage a new aluminium access platform will also be installed at the entrance level.
Domestic Installation
Stage three will be the domestic installation for both power and water supply/drainage. Power will be generated through a small generator and supplemented by any surplus solar power. New fuel tanks and supply lines will be installed. The water supply will be using an unvented cylinder, storage tanks and a house pump.
Fit out and Decoration
The final stage of the project will be the establishment of welfare, bedrooms, kitchen and decoration internally where required and externally at the lightroom.