Sizewell C - Desalination Plant Installation and Services
IDE Water Technologies Ltd, DC Dwek Corporate Finance Ltd Active Tender notice
- Buyer
- IDE Water Technologies Ltd, DC Dwek Corporate Finance Ltd
- Estimated value
- £50,000,000 as published; Contracts Finder does not say whether VAT is included
- Category
- Works
- CPV code
65122000Water desalination services- First published
- 26 Sep 2024
- Last updated
- 26 Sep 2024
- Rules
- Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds
Description
1. Sizewell C needs a sea water reverse osmosis desalination plant during the construction and initial production phase of the Sizewell C nuclear facility in Suffolk.
2. IDE Technologies and DC Dwek Corporate Finance partnered for the desalination project. IDE is one of the leading desalination and water treatment companies in the world and has a strong
international track record of desalination plant delivery.
3. The maximum capacity of drinking water required is 5,000 m3 per day with a maximum intake of 13,300 m3/day for a 15-year period. The plant needs to be constructed to a 25-year life.
4. All the desalination equipment will be supplied from Europe and assembled onsite. 1st and 2nd pass membrane skids with all the key desalination equipment will include:
a. Extensive pumping requirements and redundancy including high pressure pumps, dosing pumps, backwash pumps, limestone feed pumps, potable water and transfer pumps.
b. Pressure vessels and reverse osmosis membranes.
c Detailed pre and post treatment requirements including de-gritting, flocculation, dual membrane filters, limestone etc.
5. We will require UK based Civil and Mechanical & Electrical contractors to prepare the site and to connect the skids to the electric control rooms and to the necessary pipework.
6. All the post RO membrane water related equipment supplies need to comply with Drinking Water Inspectorate (DWI) UK water regulation 31. This includes:
a Piping
b Tanks
c. Valves
7. All electrical works will be required to UK standards. The two containerised electric rooms will need to be supplied to interconnect with the skids and control the plant. The MEICA contractor will
interconnect as required.
8. The infrastructure is critical for Sizewell and there is a 16-month timeline for the project with plant availability expected from October 2025 and project completion by January 2026.
9. We are committed to offering the opportunity to local contractors and suppliers to meet the Sizewell C local content and social value goals of the wider project. Support is offered to local suppliers by
The Suffolk Chamber of Commerce.
10. Interested parties are to register on the CompeteFor platform. https://www.competefor.com/sizewellc/ ). There is a summary of the requirements for each activity and a full package of information
(including equipment requirements complying with DWI 31) available following the signing of an NDA.
11. Due to the short time scales, pricing responses will be required during October 2024. See summaries for details.
12. Further information available directly from David Dwek ([email removed]), Gabi Verberne ([email removed]) and Hanna Yael Gabay ([email removed]).
Additional information: See attachments