# Site Steam Upgrade Project - Principal Contractor & Installation Package

The Pirbright Institute · Cancelled · Procurement termination notice

- Buyer: The Pirbright Institute
- Estimated value: £320,000 excluding VAT
- Procedure: Below threshold - open competition
- Category: Works
- CPV code: 42160000 Boiler installations
- First published: 17 October 2025
- Last updated: 7 January 2026
- Legal basis: Procurement Act 2023

## Description

The purpose of this project is to increase the Institute’s sustainability (both environmental & financial), reduce carbon emissions and safeguard the steam supply to all buildings utilising steam generated at Pirbright.
This will be achieved by a combination of the following three factors:
•	New steam main & condensate recovery system to steam users currently served by the end of life Western Boiler House.
•	Removal of inefficient and end of life Western Boiler house & increasing load on the currently underutilised, efficient, EC1 steam generation plant by 450kWh (585 kg/hr).
•	Upgrading 2 of 4 EC1 steam boilers with burners capable of 10:1 turndown ratio to enable more efficient operation at low production rates during summer months.
Contract Scope
The contract is for a single supplier to act as the Principal Contractor and complete all works as follows:
•	Supporting the Stage 4 design with client nominated designer and Project Manager 
•	Supply and Installation of EC1 steam boiler burners (x2).
•	Steam connection & packaged steam – LTHW interface to Engineering workshop 
•	Enabling works for new steam & condensate return connections located on EC1 steam distribution and WBH. 
•	Supply and installation of steam and condensate equipment. 
•	Facilitate installation & commissioning of EC1 boiler burner replacements.
•	Supply and installation of new steam connection & condensate return including all required equipment.
•	Deliver a phased changeover of steam delivery from the WBH to the newly installed connection fed from EC1. 
•	Decommission, removal and disposal of WBH and associated redundant equipment. 
•	Disconnection and isolation of gas, compressed air and mains water. 
•	Commissioning and handover including Project Information Folder (PIF) is provided to the client Project Manager.

## Awards

| Supplier | Value | Date | Status |
|---|---:|---|---|
| Not named | - | 7 Jan 2026 | Cancelled |

## Notices

- 17 Oct 2025: Tender notice (066245-2025) https://www.find-tender.service.gov.uk/Notice/066245-2025
- 7 Jan 2026: Procurement termination notice (001102-2026) https://www.find-tender.service.gov.uk/Notice/001102-2026

---