Awarded value
£482,030 as published, VAT not stated
Procedure
Call-off from a framework agreement
Category
Services
CPV code
71320000 Engineering design services
First published
30 Oct 2026
Last updated
30 Oct 2026
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

The opportunity is for the delivery of works comprising the design, construction, commissioning and handover of an operational Pumped - Passive Mine Water Treatment Scheme treating water currently discharging from Sharnberry mine, west of Hamsterley, County Durham.

This further competition seeks to appoint a contractor for Phase One services only under NEC4 ECC with Option X22.

The Mining Remediation Authority reserves the right, but is under no obligation, to proceed to Phase Two and Three with the successful contractor.

Proceeding to Phase Two and Three and awarding Phase Two and Three is subject to satisfactory agreement of target cost, risk and scope and will be represented for approval by the appropriate signatories at that time.

Awards

SupplierValueDateStatus
John Graham Construction Limited £482,030 7 Oct 2026 Active