# Shaft Secondary Lining Jumpform System

CVB JV  - Costain, Vinci C G P, Bachy Soletanche · Active · Tender notice

- Buyer: CVB JV  - Costain, Vinci C G P, Bachy Soletanche
- Estimated value: £2,500,000 (VAT not stated)
- Category: Services
- CPV code: 45200000 Works for complete or part construction and civil engineering work
- First published: 19 November 2018
- Last updated: 19 November 2018
- Rules: before the Procurement Act 2023 (published on Contracts Finder)

## Description

CVBJV is the main contractor for the East section of the Thames Tideway project.
      There are 5 site in total and 4 sites are being done with a jump form system. The Sites address
      are:
      GREPS
      Thames Water Pumping Station
      101 Greenwich High Road
      LONDON SE10 8JL
      DEPCS
      Deptford Work Site
      Crossfield Street
      LONDON SE8 3PH
      EARPS
      Earl pumping station
      Yeoman street
      LONDON SE8 5ET
      KEMPF
      Glamis Road
      St Katharine and Wapping
      LONDON E1W 3TD
      The 4 shafts are drop shafts between the existing sewers on surface and the tunnels
      of the new Thames Tideway project. Therefore, they all have a vortex structure, a vortex
      generator, and a connection to an interception chamber. Sections and elevations are available
      further in this document in Appendix A.
      The lower part of the shaft where the tunnels connect will be already built at the time
      of the construction. The jumpform system will therefore be used for the construction of the
      middle and top part of the shaft.
      The supplier will provide a jump form system (called shutter hereafter) to cast the
      secondary lining for the 4 construction site's shafts. The formwork for the lower section where
      the tunnels connect will be part of a different brief.
      The shutter will be a single face arrangement*, suitable to pour 3m lifts, which will allow
      the pour of the vortex, and fitted with 3 levels of platforms as described in the section 3.2
      Shutter Arrangement.
      The shutter will be adaptable to the different diameter of the shafts and the different
      dimensions of the vortex.
      The shutter will be able to cope with the different sequence of pour of the vortex
      generator.
      The supply will include:
      - The full design, with optional CAT 3 design check, in accordance with the deliverable
      in the section 4.2 below.
      - All the hydraulic system required for the "jumping" operation. A solution "pulled" from
      the top of the shaft, with a strand jack system can be proposed.
      - All the guiding system to control and maintain the shutter within the required 25mm
      tolerance. Manpower will need to be supplied to supervise the jumping operation, and
      the checking of tolerances.
      - The design and supply of all the embedded items needed to support the shutter. These
      items will have to meet the requirement of the permanent work repair procedure.
      - All access within the shutter itself, and working platforms
      - All access ladders and access hatches
      - All the edge protection including the net/tarpaulin/etc to block the view and/or maintain
      a closed environment
      - The adapted amount of supervision for the assembly and dismantling of the shutter.
      - Spare parts stored on site for the most common failures

## Notices

- 19 Nov 2018: Tender notice https://www.contractsfinder.service.gov.uk/Notice/091eb31f-39db-4ec5-b143-b1e8d42fb939

---
Page: https://opencontracts.uk/contract/shaft-secondary-lining-jumpform-system-b95547fd-384f-4f91-ac0e-017cf25ec606
Contains public sector information licensed under the Open Government Licence v3.0. Source: Find a Tender and Contracts Finder, Cabinet Office.