SDF Lot 3.2 East_ Forest Traffic Services Ltd A
Highways England Complete Contract award
- Buyer
- Highways England
- Estimated value
- £12,723,844 as published; Contracts Finder does not say whether VAT is included
- Awarded value
- £12,723,844 as published, VAT not stated
- Procedure
- Restricted procedure (above threshold)
- Category
- Works
- CPV code
45000000Construction work- First published
- 8 Mar 2022
- Last updated
- 8 Mar 2022
- Rules
- Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds
Description
National Highways continues to roll out the Asset Delivery model to its operational areas. There is a
requirement to deliver a range of renewal, improvement and selected small scheme construction works on the
Strategic Road Network in areas utilising specialist contractors working collaboratively with National Highways
to deliver these works. It is envisaged that this framework will straddle two Road Investment Strategy (RIS)
periods (RIS 2 and RIS 3) enabling a smooth transition between them. Works for schemes have been divided
into a number of workstreams that align with the contractors' specialisms, and will also include design.
Bandings have been introduced into the framework model to differentiate some contracting terms between
bands.
This award is for Lot 3.2 Temporary Traffic Management (region) in the East region (National Highways Areas 6 and 8).
This Lot covers the supply of materials, plant and labour for the;
- Design, installation, maintenance and removal of temporary traffic management
- Installation, maintenance and removal of temporary safety barrier systems
- Installation, maintenance and removal of temporary speed enforcement systems
- Installation, maintenance and removal of temporary CCTV systems.
- Management of breakdown recovery services
- Installation, maintenance and removal of temporary road markings and road studs, and
- Removal of existing road markings and road studs
Other duties
This scope also includes:
- Mobilisation
- Early Contractor Involvement
- Principal contractor
- Welfare facilities
- Manage Network Occupancy
- Community; and
- Contingency
Awards
| Supplier | Value | Date | Status |
|---|---|---|---|
| Forest Traffic Services Limited | £12,723,844 | 24 Feb 2022 | Active |
Notices
- 8 Mar 2022 Contract award
Contracts Finder holds the official notices, with their documents and contact details.