Buyer
Highways England
Estimated value
£21,000,000 as published; Contracts Finder does not say whether VAT is included
Awarded value
£21,000,000 as published, VAT not stated
Procedure
Restricted procedure (above threshold)
Category
Works
CPV code
45000000 Construction work
First published
28 Jul 2022
Last updated
26 Sep 2022
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

National Highways continues to roll out the Asset Delivery model to its operational areas. There is a
requirement to deliver a range of renewal, improvement and selected small scheme construction works on the
Strategic Road Network in areas utilising specialist contractors working collaboratively with National Highways
to deliver these works. It is envisaged that this framework will straddle two Road Investment Strategy (RIS)
periods (RIS 2 and RIS 3) enabling a smooth transition between them. Works for schemes have been divided
into a number of workstreams that align with the contractors' specialisms, and will also include design.
Bandings have been introduced into the framework model to differentiate some contracting terms between
bands.

This award is for Lot 2 Drainage in the East region (National Highways Areas 6 and 8).

This Lot covers the supply of materials, plant and labour to carry out;
- Construction, commissioning and removal of drainage and manhole/catch pits,
- Renewal or recycling of filter drain material,
- Renewal and repair of pipes and pipe lining,
- Renewal of ditches, swales, ponds and any other vegetative treatment systems,
- Control and disposal of contaminated material,
- Installation, commissioning and removal and renewal of flow control equipment, and
- Installation, commissioning and removal and renewal of any other drainage ancillary items including petrol interceptors and pumping station equipment

Other duties
This scope also includes:
- Mobilisation
- Early Contractor Involvement
- Principal contractor
- Welfare facilities
- Manage Network Occupancy
- Community; and
- Contingency

The scope may also include carrying out some of the duties of the Maintenance & Response Contractor and providing Incident Response (Rapid Response) when instructed.

Despite the award of the framework being earlier, contracts are issued inline with regions going live.

Awards

SupplierValueDateStatus
VolkerFitzpatrick Limited £21,000,000 26 May 2022 Active

Notices

  1. 28 Jul 2022 Contract award
  2. 18 Aug 2022 Contract award update
  3. 26 Sep 2022 Contract award update

Contracts Finder holds the official notices, with their documents and contact details.

Data