Science and Engineering Construction
Manchester Metropolitan University Active Tender notice
- Buyer
- Manchester Metropolitan University
- Estimated value
- £50,000,000 as published; Contracts Finder does not say whether VAT is included
- Procedure
- Restricted procedure (above threshold)
- Category
- Works
- CPV code
45214000Construction work for buildings relating to education and research- First published
- 18 Jan 2019
- Last updated
- 18 Jan 2019
- Rules
- Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds
Description
The University is pleased to invite detailed expressions of interest for the provision of the design and construction of the new build and potential refurbishment works on the John Dalton site for the Manchester Metropolitan University Science & Engineering faculty.
The overall works are envisaged to include the following:
- Potential demolition of the existing John Dalton West Building (circa 3,000sq.m) and service diversions.
- The construction of a new-build facility of circa 14,000sq.m including all substructures, superstructures, fixed and loose fixtures and fittings and equipment, mechanical and electrical services, drainage, external works
and external services.
- Physical links into the existing John Dalton Tower at multiple levels. This will comprise of the following approximate proportions of internal spaces:
Office space 42%
Laboratories 12%
General teaching 5%
Self-directed and social learning 6%
circulation and plant 35%
- The adjacent public realm works around new build element.
- Potential refurbishment / remodelling / minor interventions / re-occupation of the existing spaces within the existing John Dalton buildings (circa 8,000sq.m), and including the installation of the fixed and loose
fixtures and fittings and equipment.
- The demolition of the existing John Dalton East Building (Circa 15,000sq.m), and public realm work / landscaping treatment to the area.
It is envisaged the construction of the new build will begin by no later than 06 April 2021 with the new facility being operational by no later than 16 March 2023, and the refurbishment / remodelling / minor intervention of the existing buildings will begin by no later than 26 January 2022 and be completed by no later than 11 August 2023. The remaining demolition works to John Dalton East and related landscaping works will be completed by 02 December 2024.
Additional information:
In order to take part in this tender, please register your company details on our e-tendering portal:https://in-tendhost.co.uk/mmu/aspx/Home.
Once registered, interest parties can access the documents and submit an SQ response. Please note, the University is expecting to receive only SQ returns at this stage.
All clarification and correspondence will be undertaken using In-tend.
Is a Recurrent Procurement Type? : No
Notices
- 18 Jan 2019 Tender notice
Contracts Finder holds the official notices, with their documents and contact details.