# SC24047 Hartlip Hill, Newington - Mini Competition - Works over £25,000.00

Kent County Council · Complete · Contract award

- Buyer: Kent County Council
- Estimated value: £72,247 (VAT not stated)
- Awarded value: £72,247 (VAT not stated)
- Procedure: Other - 
- Category: Works
- CPV code: 45232450 Drainage construction works
- First published: 27 June 2024
- Last updated: 27 June 2024
- Rules: before the Procurement Act 2023 (published on Contracts Finder)

## Description

The Drainage Works Framework 2023 (SC22331) is used to support Kent County Council's current contracts (Highway Term Maintenance Contract, Road Asset Renewal Contract and others) to maintain it network.

Works under £25k are awarded via direct award on a rotation basis.
Works over £25k are awarded via a mini-competition process.

This notice pertains to a mini-competition exercise that was carried out under the Drainage Works Framework 2023.

Details of this mini-competition are below listed below: Aim: to find a Contractor to deliver the Hartlip Hill, Newington scheme. Dates: The scheme needs to be delivered between 2 September 2024 to 18 september 2024 - The scheme is to deliver the following outputs:

- Proposed drainage improvement to comprise installation of new carrier pipe in carriageway 
totalling approx. 125 metres of 225mm twin wall pipe to KCC/HTW/500/051 with type Z 
concrete surround. 

- New carrier pipe to connect to existing highway drainage system near junction with Lower 
Hartlip Road. Invert level of pipework to be confirmed on site but not expected to exceed 
average invert of 1.2mBGL. 

- Along route of new carrier pipe, 3no. new 1200mm catchpits to KCC/HTW/500/001 (Type 
2A) to be installed, exact depth to be confirmed on site to suit new pipe invert (with 500mm 
sump below invert level of lowest pipe) but not expected to exceed 2m overall depth. 

- 10no. new PCC trapped gullies to KCC/HTW/500/009 with D400 450x450x150 frames to 
be installed of which 5no are to replace the existing gullies, and all new and replacement 
gullies to be connected to new carrier pipe with 150mm twinwall pipe with type Z surround, 
total pipework length of 35m. 

- All existing pipework from current gullies to be abandoned and capped off at each end. 
Gully on Breach Lane to remain, with existing incoming pipe capped off. Existing outgoing 
line to remain insitu to provide outfall for the gully. 

- Manhole in footway opposite Lower Hartlip Road to be renewed (D400 600x450 clear 
opening). Manhole in carriageway to be freed up for inspection at junction with Lower 
Hartlip Road. 

- Breach Lane to be sided out both sides between Hartlip Hill and Railway bridge to remove 
excess debris at road edge and prevent pooling of water at the resident's access road. 

- All reinstatements in accordance with KCC/HTW/700/002 for carriageway road type 1, with 
all white lining and HFS surfacing to be replaced in the reinstatements.


## Awards

| Supplier | Value | Date | Status |
|---|---:|---|---|
| G & J Steele Plant Hire Ltd | £72,247 | 12 Jun 2024 | Active |

## Notices

- 27 Jun 2024: Contract award https://www.contractsfinder.service.gov.uk/Notice/1d08ea03-628f-4440-af79-a2e8d8e15184

---
Page: https://opencontracts.uk/contract/sc24047-hartlip-hill-newington-mini-competition-works-over-2500-4827e8a4-553c-4399-8726-dbab859e8ae4
Contains public sector information licensed under the Open Government Licence v3.0. Source: Find a Tender and Contracts Finder, Cabinet Office.