Estimated value
£160,000,000 as published; Contracts Finder does not say whether VAT is included
Awarded value
£160,000,000 as published, VAT not stated
Procedure
Other -
Category
Works
CPV code
45000000 Construction work
First published
2 Jul 2020
Last updated
4 Apr 2022
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

Kent County Council (the Authority) is the largest local authority in England covering an area of 3 500 km2. It has an annual expenditure of over GBP 1 billion on goods and services and a population of 1.5 million. the client provides a wide range of personal and strategic services on behalf of its residents, operating in partnership with 12 district councils and 309 parish/town councils.

The Authority consists of three operational directorates (Adult Social Care and Health, Children, Young People and Education and Growth, Environment and Transport) and one service directorate (Strategic and Corporate Services). This requirement is for the Road and Footway Asset Team who are responsible for maintaining and managing the structural and surface condition of our roads, footways and cycle tracks.

To effectively maintain our roads, footways and cycle tracks we undertake the delivery of renewal works to replace deteriorated areas which have reached the end of their useful life and preservation works to prolong the life of areas which are starting to deteriorate.

The scope of work at each site will generally entail the cold milling of the top layers of the road structure and repaving with an asphalt surface and/or binder course. All sites will include adjustments to covers and replacement of road markings and road studs where required.

Sites approaching traffic signals may require the replacement of the traffic loops. It is anticipated that many sites will require road closures and night-time working with working restrictions in place with defined times.

The project consists of multiple sites. There will be several phases of work throughout the contract period, with routine work carried out between January and November each year. The initial phases are planned as follows, subject to weather conditions:

•Phase 1 - January to March 2021
•Phase 2 - April to November 2021
•Phase 3 - January to March 2022
•Phase 4 - April to November 2022

The new contract will commence upon 1st January 2021 and will continue for a period of 24 months unless terminated in accordance with the Conditions of Contract.

Awards

SupplierValueDateStatus
G W Highways Ltd £160,000,000 20 Nov 2020 Active

Notices

  1. 2 Jul 2020 Tender notice
  2. 4 Apr 2022 Contract award