Robotics and Autonomous Systems ("R&AS") Command and Control Centre

Offshore Renewable Energy Catapult Complete Contract award

Buyer
Offshore Renewable Energy Catapult
Estimated value
£1,000,000 as published; Contracts Finder does not say whether VAT is included
Awarded value
£1,649,732 as published, VAT not stated
Procedure
Open procedure
Category
Works
CPV code
45000000 Construction work
First published
3 May 2021
Last updated
5 Jan 2022
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

ORE Catapult (https://ore.catapult.org.uk) is the UK's leading technology innovation and research centre for offshore renewable energy. ORE Catapult's vision is to be the world's leading offshore renewable energy technology centre by 2030. ORE Catapult will play a key role in delivering the UK's largest clean growth opportunity, through our mission to accelerate the creation and growth of UK companies in the offshore renewable energy sector. We will use our unique facilities and research and engineering capabilities to bring together industry and academia and drive innovation in renewable energy.
ORE Catapult is now enhancing their capabilities further by developing a Robotics and
Autonomous Systems (R&AS) facility to support the standardisation and compatibility of robot
platforms across the offshore wind industry. ORE Catapult's new facilities will offer a range of test
environments, including, but not limited to offshore testing, onsite testing, and demonstration zones.
The site will offer an end-to-end process from prototype trials to post qualification field trials on
operational assets.
The construction of the building and development of the surrounding facilities is being funded
by the North East Local Enterprise Partnership (NELEP) as part of the government's "Getting Building
Fund". The Getting Building Fund forms part of the government's New Deal for Britain and sets out
government's strategy to rebuild Britain and fuel economic recovery across the UK. As a result, the
funding for the £1 million construction is time limited.
The new facility has been designed to minimise our carbon footprint, utilising sustainable
features in keeping with our renewable energy ethos.
The construction design is being progressed to RIBA Stage 4 with Planning Permission being
sought in parallel to the tender process. All relevant and appropriate surveys are also being conducted
during this time.
Due to the time limitations for the funding, it is critical that spend and construction is
completed by March 2022 at our facility at Albert Street, Blyth, Northumbria, NE24 1LZ

Awards

SupplierValueDateStatus
Halls Construction Services Ltd £1,649,732 21 Dec 2021 Active

Notices

  1. 3 May 2021 Tender notice
  2. 3 May 2021 Tender notice
  3. 3 May 2021 Tender notice
  4. 3 May 2021 Tender notice
  5. 3 May 2021 Tender notice
  6. 5 Jan 2022 Contract award

Contracts Finder holds the official notices, with their documents and contact details.

Data