Refurbishment of Octagon Hall Pavilion Gardens Buxton Derbyshire
High Peak Borough Council & Staffordshire Moorlands District Council Complete Contract award
- Buyer
- High Peak Borough Council & Staffordshire Moorlands District Council
- Awarded value
- £2,300,000 as published, VAT not stated
- Procedure
- Open procedure (below threshold)
- Category
- Works
- CPV code
45000000Construction work- First published
- 26 Aug 2016
- Last updated
- 28 Apr 2021
- Rules
- Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds
Description
High Peak Borough Council wish to appoint a main contractor to deliver a specification of identified works to the Pavilion Gardens visitor complex in Buxton Derbyshire.
Pavilion Gardens is a unique attraction and an important tourism venue in the High Peak, a destination which has wide ranging appeal for visitors, the local community, corporate organisations, private functions and large events alike.
This is a project to correct a significant number of defects including the structural stability of the Octagon Hall at the Pavilion Gardens complex in Buxton.
The work includes a full replacement of the structural ring-beam to the Octagon Hall as well as other related structural repairs. There are further structural works required to the adjoining Octagon Lounge as well as a new flat roof to the rear of the building. There are a number of identified joinery repairs to the hall and lounge as well as stripping back the main 32 vertical columns to the hall for repaint. As such the structural scaffold will need full encapsulation. There is drainage running under the floor of the hall which requires complete replacement. The hall and lounge floors are suspended on sleeper walls which have been altered over time and require stabilising works. The actual floors to both the hall and the lounge need full replacement. In addition to these work a full upgrade of all mechanical and electrical systems is required. The finished scheme will also include for repainting of internal areas and the introduction of motorised blinds.
The estimated programme of works is 12 months. The construction budget is £2.2 million.
This exercise is being managed through the Council's E-tendering system via the West Midlands Improvement and efficiency Procurement portal. To Register an Interest and submit a tender for this opportunity please click on the link below, Select current opportunities, and then search for 'Project_19068 Restoration of the Octagon Hall Pavilion Gardens Buxton' or ITT_30292
You will need to register or log in (if you have already registered). If you have any queries or need assistance please contact [email removed]
This project has been advertised before, the previous exercise was suspended , this is now being completed under a new procedure.
Awards
| Supplier | Value | Date | Status |
|---|---|---|---|
| Gelder Ltd | £2,300,000 | 1 Jan 2017 | Active |
Notices
- 26 Aug 2016 Tender notice
- 28 Apr 2021 Contract award
Contracts Finder holds the official notices, with their documents and contact details.