REACT 1 - Round 1 Lab testing Swabs, viles, biohazard bags and PCL analysis
Department of Health and Social Care (DHSC) Complete Contract award
- Buyer
- Department of Health and Social Care (DHSC)
- Estimated value
- £8,800,000 as published; Contracts Finder does not say whether VAT is included
- Awarded value
- £8,800,000 as published, VAT not stated
- Procedure
- Negotiated procedure without prior publication (above threshold)
- Category
- Services
- CPV code
85145000Services provided by medical laboratories- First published
- 22 Sep 2020
- Last updated
- 9 Feb 2021
- Rules
- Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds
Description
Supply of Laboratory Services for provision of Testing requirements related to COVID-19.
Award of a contract without prior publication of a call for competition in the Official Journal of the European Union in the cases listed below
Extreme urgency brought about by events unforeseeable for the contracting authority and in accordance with the strict conditions stated in the directive
Explanation:
1) The Covid-19 outbreak is a Public Health Emergency of International Concern as declared by the World Health Organisation on 30 January 2020. The WHO Director General characterised Covid-19 as a pandemic on 11 March 2020.
2) A key element of ensuring an effective response to the pandemic is ensuring that there is adequate testing. Therefore, ensuring effective warehousing, assembly and transport of testing kits and associated consumables is critical to the testing value chain.
3) DHSC is satisfied the tests permitting use of the negotiated procedure without prior publication (Regulation 32(2)(c)) are met:
A. As far as is strictly necessary: the (services) were identified as strictly necessary to meet the demand to scale up the testing programme in the UK.
B. There are genuine reasons for extreme urgency: It is responding to Covid-19 immediately because of public health risks presenting a genuine emergency.
C. The events that have led to the need for extreme urgency were unforeseeable: The Commission itself confirmed: 'The current coronavirus crisis presents an extreme and unforeseeable urgency - precisely for such a situation our European rules enable public buyers to buy within a matter of days, even hours, if necessary.' (Commissioner Breton, Internal Market, 1 April 2020).
D. It is impossible to comply with the usual timescales in the PCR: It is not possible to comply with the timescales of another procedure due to the urgent requirement to ensure the services required are met.
E. The situation is not attributable to the contracting authority - DHSC has not done anything to cause or contribute to the need for extreme urgency.
Awards
| Supplier | Value | Date | Status |
|---|---|---|---|
| Eurofins Bionmis UK Limited | £8,800,000 | 18 May 2020 | Active |
Notices
- 22 Sep 2020 Contract award
- 24 Nov 2020 Contract award
- 25 Nov 2020 Contract award
- 9 Feb 2021 Contract award
- 9 Feb 2021 Contract award
Contracts Finder holds the official notices, with their documents and contact details.