# Provision of Interim Enterprise Server Infrastructure (1-3 Year Horizon)

St Basils · Complete · Contract details notice

- Buyer: St Basils
- Awarded value: £77,224
- Procedure: Below threshold - limited competition
- Category: Goods
- CPV code: 30200000 Computer equipment and supplies
- First published: 2 April 2026
- Last updated: 2 April 2026
- Legal basis: Procurement Act 2023

## Description

Objectives
•	Ensure short- to medium-term continuity of business-critical applications (e.g., QL housing management, SQL databases, Active Directory, File Server, and local backup services).
•	Provide a secure and resilient on-premises server environment that supports premises-managed software such as QL, while complementing St Basil's longer-term hybrid/cloud strategy.
•	Avoid unnecessary over-investment in hardware that may be redundant once certain systems move fully to the cloud.
•	Reduce the risk of service disruption.
•	Ensure compliance with UK data protection, cyber security, and social housing regulatory requirements.
Scope of Supply
The supplier will be expected to:
•	Propose the most appropriate interim server solution (hardware, configuration, and licensing) that meets St Basils' 1-3 year needs.
•	Balance resilience and performance with cost-effectiveness, recognising this is not a permanent, large-scale data centre investment.
•	Ensure the solution can reliably host premises-managed applications such as QL housing management and other dependent SQL-based systems.
•	Include options for limited resilience (e.g., RAID storage, dual power, or simplified HA if cost-effective).
•	Provide all required operating system and database licences.
•	Deliver, install, and configure to industry best practice (performance, resilience, and security).
•	Provide knowledge transfer and documentation to the St Basils ICT team.
•	Offer 3- to 5-year support and maintenance, recognising hardware may be retired earlier.
Reference Systems
The interim server must support and/or integrate with St Basils current applications and core systems.
Key Requirements
Suppliers should explain how their solution will:
•	Performance: Run current workloads reliably for 1-3 years.
•	Resilience: Provide core redundancy (power, RAID storage) but without over-investment in complex clustering.
•	Security: Include TPM 2.0, encryption, secure boot, and baseline hardening (Desirable).
•	Networking: Work with current infrastructure (1/10 Gb copper switching).
•	Backup/DR: Integrate with Datto/Veeam, support immutable offsite copies (cloud or equivalent).
•	Compliance: Support GDPR, Cyber Essentials Plus, and ISO27001/27002 alignment.
•	Support: Provide warranty/support cover even if hardware is retired early.
•	Sustainability: Be energy efficient and align with St Basil's' Net Zero and sustainability strategy.
Deliverables
•	Fully commissioned and documented interim server solution.
•	Licensing, warranty, and support agreements.
•	Handover to ICT staff with training/knowledge transfer.
•	Backup/restore test to evidence capability.
Supplier Response
Suppliers should include:
•	Proposed interim solution and rationale (with options, if available).
•	How the design balances performance, resilience, and cost for a 1-3 year horizon.
•	Implementation plan and timescales.
•	Total cost of ownership (hardware, software, licensing, support).
•	Warranty/support proposals that allow early retirement.
•	Evidence of similar work with housing associations/charities.
•	Social value commitments
Implementation & Costing Requirements
The supplier must ensure that their tendered price is fully inclusive of all costs required to deliver a fully operational server environment. This includes, but is not limited to:
•	Supply, delivery, and installation of all hardware and components.
•	Installation and configuration of all required software, licences, and security features.
•	Loading of existing backups/data into the new environment.
•	Testing to confirm full restoration of services, including user acceptance testing (UAT) with St Basils ICT team.
•	Verification that all core applications and integrations (see Section 4) are operating correctly.
•	Provision and configuration of any required network cabling, racks, rails, or accessories.
•	All engineer and professional services costs (installation, testing, documentation, knowledge transfer).
•	All travel, subsistence, and associated expenses.
No additional or hidden costs will be accepted. The final tendered price must cover a turnkey delivery resulting in a live, resilient, and fully operational environment.

## Awards

| Supplier | Value | Date | Status |
|---|---:|---|---|
| Intercity Technology Limited | £77,224 | 1 Dec 2025 | Active |

## Contracts

| Contract | Value | Period | Signed |
|---|---:|---|---|
| Contract 1 | £77,224 | 1 Dec 2025 to 30 Nov 2026 | 1 Dec 2025 |

## Notices

- 2 Apr 2026: Contract details notice (031116-2026) https://www.find-tender.service.gov.uk/Notice/031116-2026

---
Page: https://opencontracts.uk/contract/provision-of-interim-enterprise-server-infrastructure-1-3-year-horizon-067c47
Contains public sector information licensed under the Open Government Licence v3.0. Source: Find a Tender and Contracts Finder, Cabinet Office.