Portsmouth City Council · Active · Tender notice

- Buyer: Portsmouth City Council
- Procedure: Open procedure (below threshold)
- Category: Works
- CPV code: 34513250 Dredgers
- First published: 30 November 2021
- Last updated: 30 November 2021
- Rules: before the Procurement Act 2023 (published on Contracts Finder)

## Description

Portsmouth City Council ('the council') is inviting tenders from suitably qualified contractors to deliver dredging works and pile removal to Portsmouth International Port (PiP).
      
      PiP requires dredging to its Fountain Lake Jetty to deepen the area and the removal of 5 piles from the area. Fountain Lake Jetty (FLJ) is primarily used for the navy vessels, and it is anticipated that by deepening the seabed around this area, PIP can increase the range of cruise vessels that can utilise PiP berths.
      
      This contract will require the removal of approximately 11,000 cubic metres of silt to various depths up to 9m below Chart Datum. 
      
      The Contractor will be required to comply with the conditions of the MMO Licence for dredging/disposal of this material. 
      
      The Authority is targeting to have awarded the contract by 17th December 2021 with a subsequent commencement date of mid-January 2022.
      
      The estimated value of the contract is ?2.5-3m.
      
      This procurement timetable is detailed below and, while the council does not intend to depart from it, it reserves the right to do so at any time.
      Action                                                                                                           Target date
      Deadline for requests for clarification                                           Friday 3rd December 2021 12:00
      Tender return deadline                                                                   Friday 10th December 2021 12:00
      Award decision notified to tenderers                                           Friday 17th December 2021
      Start of work                                                                                           Mid-January 2022
      End of marine works                                                                           22nd February 2022
      End of land works                                                                                   1st May 2022
      
      Deadline for submissions of tenders is 10th December at 12:00

Additional information: 
Portsmouth City Council is currently in the process of seeking expressions of interest for dredging works and pile removal to Portsmouth International Port (PiP).

The full details and ability to express an interest will be via our e-sourcing system Intend.  This filepath will take you to the relevant area of Intend, 

https://in-tendhost.co.uk/portsmouthcc/aspx/Tenders/Current

Once on the page you can either scroll down or use the search function to find the relevant project.

Should you have any problems with the above link, please contact us on 023 9268 8235 or email: [email removed]


Is a Recurrent Procurement Type? : No

## Notices

- 30 Nov 2021: Tender notice https://www.contractsfinder.service.gov.uk/Notice/00190953-3fe2-4060-ad4f-fcd73ec19d29

---
Page: https://opencontracts.uk/contract/portsmouth-international-port-fountain-lake-jetty-capital-dredg-30723340-690f-43f9-a810-f56cc71753aa
Contains public sector information licensed under the Open Government Licence v3.0. Source: Find a Tender and Contracts Finder, Cabinet Office.