Portakabin Variation
MCA - Maritime and Coastguard Agency Complete Contract award
- Buyer
- MCA - Maritime and Coastguard Agency
- Estimated value
- £88,013 as published; Contracts Finder does not say whether VAT is included
- Awarded value
- £88,013 as published, VAT not stated
- Procedure
- Call-off from a framework agreement
- Category
- Services
- CPV code
45000000Construction work- First published
- 1 Oct 2021
- Last updated
- 1 Oct 2021
- Rules
- Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds
Description
Holy Island - Foundations and External Works - as per quote 210818 Surveys, investigations & design - Undertake foundation & drainage designs - Excavation - Strip topsoil for preservation, average depth 300mm. Excavation to reduce levels, average depth 200mm. Supply & lay one layer geotextile membrane. All excavated materials to remain on site. - Foundations & piers - Excavate pits for foundations, 800 x 800 x 600mm deep x 9nr (all excavated materials to be remain on site). Supply & lay concrete to bases, 800 x 800 x 600mm deep x 9nr. Supply & install concrete levelling piers x 9nr. Supply & lay reinforced concrete slab to vehicle parking bay including tamped finished. Optional extra to supply & lay 75mm insulation to slab area £600.00. - Foul drainage - Excavate trench & trim base, lay 110mm DIA uPVC pipe x 15 Lin m. Bed, surround & backfill with type 1 granular fill, average depth 600mm. Supply & install 450mm DIA plastic inspection chamber x 2nr (max 1.0m depth). Supply & install new manhole on existing sewer tail. Test drainage on completion. Note, we have allowed for connection into an existing combined sewer subject to drainage design & Local Authority approval. - Storm drainage - Supply & install access gullies to rain water pipes x 2nr. Note, we have allowed for connection into an existing combined sewer subject to drainage design & Local Authority approval. - Ducts - Excavate trench & lay sand blinding x 15 Lin m, supply & lay 2nr 100mm DIA general purpose ducts each complete with 2nr bends, draw ropes & marker tape. - Water supply - Excavate trench & lay 25mmMDPE water main, lay warning tape & backfill. Alterations & connection to existing water system. Trace heating of above ground water pipework. - Electrical supply - Provisional Sum £4,000.00 for the supply & installation of submain from adjacent public toilets, 25m - Paving & surfacing - Lay & compact Type 1 granular material to pathway, 100mm thick x 30m2. Lay & compact Type 1 granular material to par
Awards
| Supplier | Value | Date | Status |
|---|---|---|---|
| Portakabin Limited | £88,013 | 8 Sep 2021 | Active |
Notices
- 1 Oct 2021 Contract award
Contracts Finder holds the official notices, with their documents and contact details.