OpenContracts

Phase I Utilities Works Package

Rex Procter & Partners LLP Planning Planned procurement

Buyer
Rex Procter & Partners LLP
CPV code
45000000 Construction work
First published
7 Aug 2018
Last updated
11 Feb 2019
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

The Project known as Phase 1 Utility Infrastructure Works Package comprises the following:

Section 1 - Rugby Club House
Section 2 - Onsite Main Utilities Infrastructure
Section 3 - Offsite Main Utilities Infrastructure

An outline planning application was submitted to Rochford District Council (15/00776/OUT) and permission was granted on the 14 March 2016.

The Project is to provide new utility supplies to serve the proposed development including all contestable and the management of the non-contestable works.

As part of the phase 1 works, utility infrastructure service provisions are to be established, including Electrical, Gas, and Water and Telecommunication infrastructure services. Each utility infrastructure service (contractor's proposals) is to be designed to the Employers Requirements and in accordance with the projected capacity demands of the Phase 1 development area, and consider suitable capacity provisions for the on-going development phases. As part of the design development process, careful consideration should be given to the short, medium and long term capacity projections.

Tenderers must express their interest and confirm an intention to bid in order to receive Clarification Questions and responses to Clarification Questions.

All clarifications to tender queries will have company names removed and will be circulated to all tenderers unless the tenderer submitting the Request for Information/Clarification Questions indicates that this is commercially sensitive in the e-mail subject.

Additional information: The following list of tender documents form the basis of the contract documentation for this project.

Section 1 Invitation To Tender
Section 2 Preliminaries
Section 3 Form Of Tender
Section 4 Contract Sum Analysis
Section 5 Employer's Requirements Specification
Section 6 Appendices
Appendix A Employer's Requirements Drawings
Appendix B PCI
Appendix C Contract Amendments, Bonds, Warranties
Appendix D Engineer's SI Report
Appendix E Other information

Notices

  1. 7 Aug 2018 Planned procurement
  2. 6 Sep 2018 Planned procurement
  3. 11 Feb 2019 Planned procurement

Contracts Finder holds the official notices, with their documents and contact details.

Data