## Description

The Council is looking to appoint to two Lots. Bidders may bid for one or both Lots separately.

Lot 1 Refurbishment of Woolaway Houses North Taunton - Phase E

The Works comprise the complete refurbishment of the properties on the basis that all the
external walls, windows and doors are replaced; all roofing is stripped and re-laid; and a full
package of internal replacement and upgrading is provided all as shown and described on
the tender and contract drawings and the specifications.
The Works will be executed in Sections using the following parameters:

Section 1: Works to 4 Bodmin Road; 9, 25 & 27 Dorchester Road Date of Possession to be 4
calendar weeks after the signing of the JCT Contract. The Date for Completion to be 20
calendar weeks after the Date of Possession.
Section 2: Works to 17, 23, 33 & 35 Dorchester Road Date of Possession to be 2 weeks after
the completion of Section 1. The Date for Completion to be 16 calendar weeks after the Date
of Possession.

Lot 2 Refurbishment of Woolaway Houses Oake

The Works comprise the complete refurbishment of the properties on the basis that all the
external walls, windows and doors are replaced; all roofing is stripped and re-laid; and a full
package of internal replacement and upgrading is provided all as shown and described on
the tender and contract drawings and the specifications.
The Works will be executed in Sections using the following parameters:
Section 1: Works to 21, 23 and 24 Oake Close Date of Possession to be 4 calendar weeks
after the signing of the JCT Contract. The Date for Completion to be 20 calendar weeks after
the Date of Possession.
Section 2: Works to 17, 18 and 19 Oake Close Date of Possession to be 2 weeks after the
completion of Section 1. The Date for Completion to be 16 calendar weeks after the Date of
Possession.
Section 3: Works to 2, 3 and 4 Oake Close Date of Possession to be 2 weeks after the
completion of Section 2. The Date for Completion to be 16 calendar weeks after the Date of
Possession.
Section 4: Works to 25 Oake Close Date of Possession to be 2 weeks after the completion of
Section 3. The Date for Completion to be 16 calendar weeks after the Date of Possession.


## Notices

- 21 Oct 2022: Tender notice https://www.contractsfinder.service.gov.uk/Notice/2415b556-4eb0-4938-84c6-33b69f0ad46d

---
Page: https://opencontracts.uk/contract/north-taunton-and-oake-woolaway-refurbishment-7a7051a5-cabf-4753-9672-42ecb2cdb847
Contains public sector information licensed under the Open Government Licence v3.0. Source: Find a Tender and Contracts Finder, Cabinet Office.