New Build Housing at Eign Mill Road and Highmore Street, Hereford
Connexus Housing Group Complete Contract award
- Buyer
- Connexus Housing Group
- Estimated value
- £2,656,600 as published; Contracts Finder does not say whether VAT is included
- Awarded value
- £2,787,266 as published, VAT not stated
- Procedure
- Restricted procedure
- Category
- Works
- CPV code
44000000Construction structures and materials; auxiliary products to construction (except electric apparatus)- First published
- 25 Mar 2020
- Last updated
- 25 Mar 2020
- Rules
- Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds
Description
There is currently two main sites to be developed under a single Design and Build Contract.
Eign Mill Road, Hereford - The demolition of 5Nr existing bungalows and the design and construction of 9Nr houses and 2Nr bungalows one of which will be a type M3 unit. Planning approval has been obtained. Planning reference P183891/F
Highmore Street, Hereford - The demolition of 5Nr existing bungalows and the design and construction of 6Nr houses and 1Nr type M3 bungalow. The units are split across two adjacent sites approximately 100 metres apart. Planning approval has been obtained. Planning reference P183889/F and P183890/F.
There is currently a proposal for a further 12Nr units to be developed at Pine Grove, Hereford but this is still subject to planning. The intention is to negotiate the additional 12Nr unit scheme with the contractor of the initial contract for Eign Mill Road and Highmore Street.
Awards
| Supplier | Value | Date | Status |
|---|---|---|---|
| G.P. Thomas Construction | £2,787,266 | 3 Mar 2020 | Active |
Notices
- 25 Mar 2020 Contract award
Contracts Finder holds the official notices, with their documents and contact details.