OpenContracts

MCHFT RAAC Structural Engineering & Survey Inspections

MID Cheshire Hospitals NHS Foundation Trust Complete Contract award

Buyer
MID Cheshire Hospitals NHS Foundation Trust
Estimated value
£2,289,010 as published; Contracts Finder does not say whether VAT is included
Awarded value
£2,289,010 as published, VAT not stated
Procedure
Call-off from a framework agreement
Category
Services
CPV code
71312000 Structural engineering consultancy services
First published
2 Oct 2025
Last updated
2 Oct 2025
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

Leighton Hospital, built in the late 1960s and opened in 1972, is one of the most cost-effective acute hospitals and is a sister hospital to Airedale NHS Foundation Trust. Much of the original structure incorporates RAAC panels in its roof and walls, with over 16,500 roof panels and various internal and external wall panels, mostly non-load bearing. Extensive inspections and testing have been conducted, with a risk rating system (P1 to P4) applied to prioritise repairs. Ongoing remedial work includes the installation of steel frameworks, Unistrut supports, and timber reinforcements to address high-risk areas while maintaining hospital operations. RAAC management is overseen by the Estates team and supported by a detailed Structural Risk Appraisal and RAAC Management Plan.

Mid Cheshire Hospitals NHS Foundation Trust undertook a further competition for Reinforced Autoclaved Aerated Concrete (RAAC) structural engineering and survey inspection services under the NHS Shared Business Services Healthcare Planning, Construction Consultancy and Ancillary Services Framework (SBS10190), Lot 3 - Civil and Structural Engineering.

The services is required to deliver both structural engineering and surveying services, with data to be managed through a Common Data Environment provided by BIS Consult. This service will support a multi-year mitigation programme through to the hospital's planned replacement in 2032, after which the current buildings are expected to be demolished.

The contract duration will be seven (7) years, up to the anticipated demolition of the current buildings in 2032. Should demolition be delayed beyond this date, the Contracting Authority reserves the right to extend the contract accordingly, subject to mutual agreement and continued service requirements.

Awards

SupplierValueDateStatus
Mott MacDonald Limited £2,289,010 2 Oct 2025 Active

Notices

  1. 2 Oct 2025 Contract award

Contracts Finder holds the official notices, with their documents and contact details.