Low Voltage Infrastructure and Generator Replacement at Police HQ, Portishead
Avon and Somerset Constabulary Active Tender notice
- Buyer
- Avon and Somerset Constabulary
- Estimated value
- £800,000 as published; Contracts Finder does not say whether VAT is included
- Procedure
- Open procedure
- Category
- Goods
- CPV code
31000000Electrical machinery, apparatus, equipment and consumables; lighting- First published
- 10 Feb 2017
- Last updated
- 10 Feb 2017
- Rules
- Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds
Description
LV ELECTRICAL & GENERATOR REPLACEMENT - AVON & SOMERSET FORCE HQ
Project Scope
Avon and Somerset Constabulary propose to carry out replacement and improvements to their LV mains switchgear and associated equipment due to the majority of the fittings being time expired or in poor condition.
In addition, the scheme involves the installation of new 800kVA generator sets to act as permanent standby provision.
Proposed Works
The proposed works include the following main elements:
Mechanical & Electrical:
• Installation of temporary supply arrangements to maintain existing site infrastructure.
• Replacement of life expired LV switchgear.
• Disconnection of existing site generators redundant from these works.
• Provision of 4No. new 800kVA generator sets.
• Provision of new Uninterruptible Power Supply cabinet to support the existing critical services.
• Alteration of existing site infrastructure.
Fabric:
• New reinforced concrete slab base to form new generator set compounds.
• Timber hit & miss fencing and access gates to the generator compound.
• Associated below ground storm drainage adaptions.
• Provision of new Armco vehicle barriers.
• Car Park road lining.
• Below ground trenching works for the new cabling.
• Associated holes and apertures into the designated buildings.
Tender Escort
Tenderers will be given access to the site for pricing purposes on either Thursday 9th or Friday 10th February 2017 between 10.00am - 12noon.
Pricing
The tenderer shall fully price the specification of works, inclusive of all M&E works, associated structural and builders' work. The identified provisional sums as detailed shall also be included. The tenderer shall also include as stated a 5% contingency on their total tender figure.
Programme
Date for possession of site: 5 June 2017
Commencement of construction works: 5 June 2017
Date for completion of works: 15 September 2017
Length of Contract: 15 weeks
Notices
- 10 Feb 2017 Tender notice