# Kingsway Tunnel Refurbishment (Dado Panels)

Merseytravel · Planned · Pipeline notice

- Buyer: Merseytravel
- Estimated value: £3,800,000 excluding VAT
- Procedure: Competitive flexible procedure
- Category: Works
- CPV code: 45262660 Asbestos-removal work
- First published: 1 May 2026
- Last updated: 1 May 2026
- Legal basis: Procurement Act 2023

## Description

The contracting authority intends to procure a suitably qualified contractor to undertake refurbishment and/or replacement works to the dado panel system within the Kingsway Tunnel.
The Kingsway Tunnel is a critical piece of transport infrastructure, and the existing dado panels-forming part of the tunnel lining and safety system-require upgrade to ensure continued compliance with current safety standards, durability requirements, and operational performance.
The appointed contractor will be responsible for delivering a comprehensive programme of works, which is expected to include, but not be limited to:
Condition Assessment and Surveys: Detailed inspection of existing dado panels, fixings, and supporting structures to determine extent of deterioration, defects, and required interventions.
Design Development: Finalisation of design solutions for refurbishment and/or replacement, including materials selection, fire resistance, impact resistance, and compliance with relevant UK and EU tunnel safety standards.
Removal and Installation Works: Safe removal of existing panels where required and installation of new or refurbished dado panels, including all associated fixings, supports, and interfaces with tunnel systems.
Integration with Tunnel Systems: Coordination with existing tunnel infrastructure, including drainage, ventilation, lighting, and emergency systems, ensuring no adverse impact on operations or safety.
Traffic and Operational Management: Planning and implementation of works to minimise disruption, including phased delivery, night-time or partial closures, and coordination with tunnel operations.
Health, Safety, and Compliance: Adherence to all relevant health and safety legislation, including working in confined spaces and live highway environments, with robust risk management procedures.
Environmental Considerations: Management of waste, materials, and environmental impacts in line with applicable regulations and sustainability objectives.
Testing, Commissioning, and Handover: Inspection and verification of installed systems, ensuring compliance with specifications and provision of as-built documentation.
The works will be delivered in a highly constrained operational environment, requiring careful planning, stakeholder coordination, and experience in similar tunnel or highway infrastructure projects.
This procurement seeks to appoint a contractor with proven expertise in tunnel refurbishment, highway infrastructure works, and installation of specialist panel systems. The project outputs will contribute to the long-term safety, resilience, and operational efficiency of the Kingsway Tunnel.

## Notices

- 1 May 2026: Pipeline notice (040553-2026) https://www.find-tender.service.gov.uk/Notice/040553-2026

---
Page: https://opencontracts.uk/contract/kingsway-tunnel-refurbishment-dado-panels-06905f
Contains public sector information licensed under the Open Government Licence v3.0. Source: Find a Tender and Contracts Finder, Cabinet Office.