OpenContracts

Kingston Station Cycle Hub

The Royal Borough of Kingston upon Thames Active Tender amendment

Buyer
The Royal Borough of Kingston upon Thames
Estimated value
£1,000,000 as published; Contracts Finder does not say whether VAT is included
Procedure
Open procedure
Category
Works
CPV code
44112000 Miscellaneous building structures
First published
25 May 2018
Last updated
2 Jul 2018
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

The purpose of this contract package is to appoint a principal contractor to finalise contractor designed elements like steelwork connections, undertake construction of civil works to the substructure, fabricate and undertake all ancillary elements of steelwork systems to the Cycle Hub, transport the hub superstructure from off-site fabrication facilities to the site in Kingston and installation, undertake the fitting of all equipment and facility connections, which comprise of, but are not limited to: internal and external lighting, CCTV, lift, shops, security, gas, potable water, foul sewer, and electrical. The Principal Contractor will have the responsibility of all coordination, permitting approvals with stakeholders, including Network Rail approvals for temporary works (craning and propping) and civil works in close proximity to railway assets, and South Western Railways for allocation of parking spaces and CCTV to the internal structure of the Hub.

For this purpose, the fabrication and construction shall be led by a reputable civil engineering company with proven similar experience, to achieve the safe delivery of this project on time and budget.

Technical Disciplines Within Scope

The project requires construction and fabrication services and expertise in the following specialist areas (as defined in the procurement categories):
• Civil Engineering (highways & structures);
• Hub building steelwork fabrication, assembly and ancillaries (surface treatments, steel surface protection systems, connections)
• MEP engineering (including internal lighting and CCTV)
• Lift procurement and installation
• Lighting of internal and outdoor structures
• Heavy Transportation and Craning operation (temporary works)
• Traffic Management
• Coordination / Communication / Stakeholders Engagement
• Health & Safety

Brief summary statement
The proposed works comprise construction of reinforced concrete foundations and piles, fabrication and installation of a two storey steel Cycle Hub, and internal fittings (Shops, workshop, MEP, CCTV and lift). The proposed Cycle Hub is to be located to the west of Kingston Station, and east of the proposed new River Link and Cycle Bridge.
The design of the proposed Cycle Hub has incorporated suitable and safe methods of construction. This will minimise any impact to Network Rail infrastructure. This includes off site fabrication of the superstructure in factory conditions, which reduces work on site and, in particular, work at height.
It is intended that the steel elements of the hub are transported to site in uniform modular section, and then erected and connected on site. However, the bidders can suggest other methods if safety can be improved and costs reduced.
A Form 1 and Form 2 approval will need to be obtained through Network Rail's Asset Protection team.

Notices

  1. 25 May 2018 Tender notice
  2. 2 Jul 2018 Tender amendment

Contracts Finder holds the official notices, with their documents and contact details.

Data