HS2 C1 ALIGN JV - Jetty Dismantling and Removal

ALIGN JV (Bouygues Travaux Publics, VolkerFitzpatrick and Sir Robert McAlpine) Active Tender notice

Buyer
ALIGN JV (Bouygues Travaux Publics, VolkerFitzpatrick and Sir Robert McAlpine)
Estimated value
£2,500,000 as published; Contracts Finder does not say whether VAT is included
Category
Works
CPV code
45244100 Marine installations
First published
12 May 2023
Last updated
12 May 2023
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

To facilitate the construction of the Colne Valley Viaduct, Align JV had to construct a temporary Jetty over the various water courses around the Colne Valley region. This was formed of a tubular piled foundation, steel frame structure, and capped with purpose made precast planks.
The works will consist of the removal of the jetty and finishes (barriers, lamp posts etc.) over water, with the tubular piles cut off below bed level of the various watercourses (piles cannot be removed completely and need to be cut down (probably from within piles)).
All materials removed will either taken back to main compound and disposed of by Align and/or removed from site and disposed of by the selected sub-contractor.
The scope will also include the burning/removal of pile cap sheet pile cofferdams to top of pile cap within the lakes.
The scope will also include the removal of temporary causeway and associated works (fill materials, tensioning bars, sheet piles (cut to ground level) and the like)

Additional information: This will be a highly sensitive operation and in close proximity to the permanent asset, so appropriate consideration will need to be taken for the type of equipment to be used and the methods. A full ITT would be issued to the shortlisted tenderers outlining the constraints.

Notices

  1. 12 May 2023 Tender notice

Contracts Finder holds the official notices, with their documents and contact details.