## Description

Highways Verge Works
North of A171
Creation of Bridleway Crossing with Holding Area as detailed in DMRB Vol. 6, S3, part 5, sect. 9
Lined with geotextile and surfaced with 150mm compacted type 1 aggregate and finished with a compacted 25mm layer of 6mm- dust.
Install drainage provision to prevent surface water discharging onto the highway
Extension of tarmac area and extension of dropped kerb from field access to crossing area (approx. 4m x 1m)
Crossing to be constructed in accordance with Standard Detail B4 and E6W
Existing highway drainage grip relocated downhill of the proposed crossing
Surface levelling along bridleway route, relocation of stone mound
South of A171
Creation of Bridleway Crossing with Holding Area as detailed in DMRB Vol. 6, S3, part 5, sect. 9
Lined with geotextile and surfaced with 150mm compacted type 1
aggregate and finished with a compacted 25mm layer of 6mm-dust.
Provision to prevent surface water discharging onto the highway
Installation of 5m of dropped kerb to the highway surface
Crossing to be constructed in accordance with Standard Detail B4 and E6W
Ancillary Works
Fencing
Erection of approximately 150m additional stock fence (15cm x 15cm uprights centred at 1.5m) as shown on plan 2
Gates
Installation of 1 no. 5'6ft bridle gate and 2 no. 12ft field gate and side rails to leave stock proof  at location shown on plan 2
Road Surfacing
Installation of a 10m wide band of high friction surfacing to HD37 (DMRB 7.5.2) the width of the carriageway (similar colour to the carriageway)
Signage
Erection of 2 no. triangular warning signs to be erected to warn drivers eastbound and westbound of the crossing point to DMRB Volume 8 Section 2 Part 2 (TD 26/17)
Dry Stone Wall
Dismantle and rebuild approximately 10 m of Dry Stone Wall plus supply stone for and construct an additional 10m of stone wall in accordance with plan 2
Spoil Management
Excess spoil to be relocated to Skelder top car park and used to re-profile existing bunds

## Notices

- 24 Apr 2018: Tender notice https://www.contractsfinder.service.gov.uk/Notice/b92b52e2-8663-49fa-9949-da7275fec493

---
Page: https://opencontracts.uk/contract/highways-works-on-a171-c9e9a813-3c82-43f2-a08f-95c593d80117
Contains public sector information licensed under the Open Government Licence v3.0. Source: Find a Tender and Contracts Finder, Cabinet Office.