GB-Shrewsbury: Deans Culvert
Shropshire Council Active Tender notice
- Buyer
- Shropshire Council
- Estimated value
- £500,000 as published; Contracts Finder does not say whether VAT is included
- Procedure
- Open procedure
- Category
- Works
- CPV code
45221220Culverts- First published
- 3 Feb 2020
- Last updated
- 3 Feb 2020
- Rules
- Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds
Description
Deans Culvert is a single span brick pipe culvert with concrete faced headwall and
training wall to the upstream end, there are no wingwalls / headwall to the downstream
end. There are no parapets to this structure, however there is a well-established hedge
adjacent to the carriageway (note:- this hedge has been cleared for access and
replaced with a temporary timber fence as shown on Drawing 62240651-T-103). The
structure is situated under the B4373 which is south of Broseley at National Grid
Reference SJ 680 003.
The culvert was monitored as part of a BD79 inspection regime, on a monthly basis
until May 2012, and then annually until March 2017, to assess movement to the
existing cracks and the shape of the culvert. There was found to be no significant
changes in the readings and repairs were undertaken in early 2014, comprising of
pointing radial cracks and infilling any voids. Some of the pointing has exhibited
hairline cracking and there is a transverse crack to the soffit of the crown running from
the downstream end into the culvert by around 8m. The culvert also exhibits a "sag" in
the invert of around 250mm. Shropshire Council have now requested a liner be
installed, but without reduction to the culverts capacity.
The proposed works include: -
Implementation, maintenance and removal of traffic management system;
Construction of temporary access to the upstream end of the culvert;
Excavation of the carriageway to accommodate a 300mm diameter overpumping
pipe;
Reinstatement of carriageway once the pipe is installed;
Site Clearance;
Damming and temporary diversion of the watercourse (pumping) to create a
dry working environment through the culvert;
Installation of concrete to the underside and front of the downstream invert;
Placing of 350mm - 500mm diameter stone to the invert at the downstream
end of the structure;
Installation of Cured in Place Pipe (CIPP) liner.
Grout to void areas behind the new CIPP liner.
Erection of a timber fence to the upstream and downstream verge directly
above the culvert;
Provision of new hedgerow
Erection of a new timber gate to the upstream access.
Removal of the temporary access and making good site.
Planned start date 15 June 2020 and planned finish date 10 July 2020
Additional information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement.
Notices
- 3 Feb 2020 Tender notice