# GB-Edinburgh: MAJOR REFURBISHMENT OF PLADDA LIGHTHOUSE

Northern Lighthouse Board · Complete · Contract award

- Buyer: Northern Lighthouse Board
- Estimated value: £198,756 (VAT not stated)
- Awarded value: £198,756 (VAT not stated)
- Procedure: Not specified
- Category: Works
- CPV code: 45442121 Painting work of structures
- First published: 26 April 2024
- Last updated: 26 April 2024
- Rules: before the Procurement Act 2023 (published on Contracts Finder)

## Description

Refurbishment work. Painting and glazing work. Painting work. Painting work of buildings. Painting and protective-coating work of structures. Painting work of structures. Pladda Lighthouse is situated on the pear-shaped Island of Pladda half a mile off the South East corner of Arran at Latitude 55o 25.5' N, Longitude 05o 07.3' W. The current light, which was automated in 1990, stands 29 meters high and is situated 40 metres above sea level. The light has a white flashing character (3) every 30 seconds giving a nautical range of 17 miles. The only property the NLB currently own on the Island is the lighthouse tower, the smaller tower below, the link corridor building between both towers, and the solar panel structure. All remaining buildings and land are privately owned. Due to the location of this site, the majority of materials and equipment will be transported to and from site via NLB Tender & Helicopter. Main Items of work: The main items of project work are as listed below:-
      
      1.Carry out a full Asbestos Refurbishment / Demolition Survey on all NLB operational buildings prior to the commencement of any work. The survey, sample collection and sample analysis must be carried by a UKAS accredited contractor in accordance with ISO 17020, ISO 17025 and Health and Safety Executive Guidance Notes; HSG 248, Asbestos: The analysts' guide for sampling, analysis and clearance procedures" and HSG264, Asbestos: The survey guide.
      2.The Principal Contractor is expected to test the existing 'HCL' fall arrest system and re-certify it if necessary before use. The Principal Contractor is to provide the Project Leader with all relevant test certification for record and audit purposes.
      3.Deliver all plant/materials/camp to NLB Oban packaged for helicopter underslinging
      4.Land plant/materials/camp on site and establish site.
      5.Full redecoration of the station
      
      Key dates:
      
      10/7/2024 - Contractor to deliver all plant/materials to NLB Oban for loading aboard the NLV Pharos - all loads to be prepared as per NLB Helicopter underslinging guidance
      
      24/7/2024 - NLB Ship and Helicopter will deliver all plant/materials to site - contractor must be on site to receive loads. NLV Pharos will be available to provide accommodation while site camp is constructed
      
      29/10/2024 - NLB Ship and Helicopter will clear site and return all contractor's plant/materials to NLB Oban for collection - all loads to be prepared and weighed as per NLB Helicopter underslinging guidance with dangerous goods signed off accordingly

## Awards

| Supplier | Value | Date | Status |
|---|---:|---|---|
| TRAC HLM Ltd | £198,756 | 25 Apr 2024 | Active |

## Notices

- 26 Apr 2024: Contract award https://www.contractsfinder.service.gov.uk/Notice/1c4a5156-616e-47eb-8098-98c6bfda3f65

---