Further Competition for Hereford Western Bypass Phase 1
Due North Limited Complete Contract award update
- Buyer
- Due North Limited
- Estimated value
- £1,859,961 as published; Contracts Finder does not say whether VAT is included
- Awarded value
- £1,859,961 as published, VAT not stated
- Procedure
- Other - Procurement
- Category
- Works
- CPV code
45200000Works for complete or part construction and civil engineering work- First published
- 18 May 2026
- Last updated
- 18 May 2026
- Rules
- Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds
Description
A further competition process was carried out by Herefordshire Council under Lot 4 of the Pagabo Civils and Infrastructure Framework Agreement.
The project is for the Design and Build of the first phase of the Hereford Western Bypass (HWB1) . The route of the proposed HWB1 is approximately 3.5 km in length and is located on the outskirts to the southwest of Hereford.
The procurement procedure was undertaken as a Two Stage Design & Build process. This was the tender for Stage One Assessment, to result in an Award for a Pre-Construction Services Agreement (PCSA) to one successful contractor. The successful Contractor will work with the council under the PCSA, with the intention to then award the full Design & Build Contract. This is subject to an affordable Contract Sum and realistic Programme to complete all Works.
Awards
| Supplier | Value | Date | Status |
|---|---|---|---|
| John Graham Construction Limited | £1,859,961 | 30 Apr 2026 | Active |
Notices
- 18 May 2026 Contract award
- 18 May 2026 Contract award update
Contracts Finder holds the official notices, with their documents and contact details.