OpenContracts

FM22127 Transition Work - ICTEM Lab 212-14 refurbishment to UKRI

UK Shared Business Services Limited Complete Contract award

Buyer
UK Shared Business Services Limited
Estimated value
£45,800 as published; Contracts Finder does not say whether VAT is included
Awarded value
£45,800 as published, VAT not stated
Procedure
Competitive quotation (below threshold)
Category
Services
CPV code
45100000 Site preparation work
First published
31 Aug 2022
Last updated
31 Aug 2022
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

***** THIS IS AN AWARD NOTICE, NOT A CALL FOR COMPETITION ***** This procurement is being concluded following a competitive procurement exercise.

1. Provide a site office and all other required facilities in accordance with Construction (Design and Management) regulations 2015 (CDM 2015)
2. Provide a site manager to oversee the work on day-to-day basis.
3. Provide all necessary storage solutions for all materials which will need to be sourced in advance of the work on the site without obstructing any traffic (road and pedestrian) including the hospital's supply and fire escape routes.
4. All material necessary to execute the work should be sourced, delivered and stored on the site by no later than the 1st of October 2022. For any clarification in
terms of material/finishes please refer to the attached architect's drawing which can be found within Appendix A - Proposed Plan - Flow Facility Lab, Rooms 212,214.
5. All work is to be executed on site within a period of 4 weeks. It is anticipated that the works on site shall commence on or around the 16th of October 2022 once all
mobilisation/off site manufacturing is complete.
6. Provide verification of all infrastructure services before and after. You will be required to use an approved commissioning engineer by the Landlord, Imperial College (IC). It is expected that the commissioning engineer shall be required on site for 2 days and therefore bidders are to factor this into their pricing.
7. Provide a full MEP design solution in line with the Landlord's O&M design parameters and provide final verification (commissioning to take the design into account).
8. All work is to be done with no interruption to day-to-day operation of the LMS building.
9. Make good all building fabric including carpets and decoration by repairing and restoring to a 'like new' standard.
10. The successful contractor is to make their own arrangements for the disposal of all rubbish generated on the site daily, no rubbish accumulation will be allowed on the site.
11. Clean the site once all work is completed.

Awards

SupplierValueDateStatus
Servol Limited £45,800 20 Jul 2022 Active

Notices

  1. 31 Aug 2022 Contract award