Engineering Stage 5 (ES5) and Enabling Works for upgrade to Witton and Aston Rail Stations
West Midlands Combined Authority Complete Contract award notice
- Buyer
- West Midlands Combined Authority
- Awarded value
- £4,221,520 excluding VAT where the notices give it
- Procedure
- Direct award
- Category
- Works
- CPV code
45230000Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork- First published
- 5 Nov 2026
- Last updated
- 5 Nov 2026
- Legal basis
- Procurement Act 2023
Description
The upgrade of Witton and Aston stations was identified as a Mayoral priority in April 2025, with delivery of the interventions to be completed ahead of the UEFA Euro 2028, which nearby Villa Park Stadium is set to host four international football matches.
We are now proposing to continue the development phase into Engineering Stage 5 with Network Rail and in parallel commence advanced enabling works activities ahead of a targeted completion ahead of UEFA Euro 2028.
Design Development
The project has proceeded through design stages ES3 and ES4 and now needs to progress to detailed design. This is Engineering Stage 5 (ES5) in Network Rail's PACE framework. Additional elements for the next design phase include Overhead Line Equipment (OLE) isolation works to minimise disruption to the network in advance of the enabling works and core construction work phases, preliminary / personnel costs, contingency, and property and planning costs associated with the Waterworks site.
Enabling Works Need
To achieve programme and completion in advance of UEFA Euro 2028, enabling works are required in parallel to ES5 (detailed design) development.
Awards
| Supplier | Value | Date | Status |
|---|---|---|---|
| Network Rail Infrastructure Limited | £4,221,520 | 30 Oct 2026 | Pending |
Notices
- 5 Nov 2026 Transparency notice 105195-2026
- 5 Nov 2026 Contract award notice 105286-2026
Find a Tender holds the official notices, with their documents and contact details.